Question # 73

After preparing a probability distribution of cost outcomes for a project, the estimate with a 20% probability of being exceeded is approximately one standard deviation:

A.

Below the mean.

B.

Above the mean.

C.

Below the median.

D.

Above the median.

Full Access
Question # 74

You are in process of developing an approximation of the costs of resources needed to complete each schedule activity. Which of the following is the least helpful input?

A.

WBS, WS dictionary

B.

Market place conditions, commercial databases

C.

Estimate Costs policies/ templates, historical information, project team knowledge

D.

Activity cost estimates, activity cost estimate supporting detail

Full Access
Question # 75

The stakeholder's influence is greatest at the ______ of the project.

A.

beginning

B.

closing

C.

controlling

D.

none

Full Access
Question # 76

How many communication channels will be required in a project having five individual participants?

A.

10

B.

12

C.

4

D.

5

Full Access
Question # 77

Reverse analysis is a tool or technique in all of the following processes EXCEPT:

A.

Monitor and Control Risks

B.

Activity resource estimation

C.

Cost estimation

D.

Determine Budget

Full Access
Question # 78

You have been assigned to a project where the objective is to create a new building. You are in charge of the demolition phase of this project, and you report to the project manager in charge of this project. You have been hired on contract and will be released at the completion of the demolition phase. What type of organizational structure you are working for?

A.

Projectized organization

B.

Weak matrix organization

C.

Balanced matrix organization

D.

Functional organization

Full Access
Question # 79

You are project manager and working on gathering requirements and estimating for the project. Which process group are you in?

A.

Planning

B.

Monitoring and Controlling

C.

Executing

D.

Initiating

Full Access
Question # 80

Which process involves formal product acceptance and end of a project?

A.

Executing processes

B.

Planning processes

C.

Controlling Processes

D.

Closing processes

Full Access