After preparing a probability distribution of cost outcomes for a project, the estimate with a 20% probability of being exceeded is approximately one standard deviation:
You are in process of developing an approximation of the costs of resources needed to complete each schedule activity. Which of the following is the least helpful input?
How many communication channels will be required in a project having five individual participants?
Reverse analysis is a tool or technique in all of the following processes EXCEPT:
You have been assigned to a project where the objective is to create a new building. You are in charge of the demolition phase of this project, and you report to the project manager in charge of this project. You have been hired on contract and will be released at the completion of the demolition phase. What type of organizational structure you are working for?
You are project manager and working on gathering requirements and estimating for the project. Which process group are you in?