Question # 41

________ must be measured regularly to identify variance from the plan.

A.

Project performance

B.

Stakeholder requirements

C.

Schedule progress

D.

Cost and schedule

Full Access
Question # 42

The ability of a product to be used for different purposes at different capacities and under different conditions determines its ____________.

A.

Usability

B.

Flexibility

C.

Operability

D.

Availability

Full Access
Question # 43

A structured tool, usually industry or activity specific, used to verify that a set of required steps has been performed is called _________.

A.

Quality Policy

B.

check List

C.

Trenc' Analysis

D.

Paieto Diagram

Full Access
Question # 44

How much time does the typical project manager spend communicating both formally and informally?

A.

40-60%

B.

50-70%

C.

60-80%

D.

75-90%

Full Access
Question # 45

Which process involves coordinating people and other resources to carry out plan?

A.

Executing processes

B.

Planning processes

C.

Controlling Processes

D.

Closing processes

Full Access
Question # 46

A contingency plan is executed when _____________.

A.

A risks is identified

B.

An identified risk occurs

C.

When a workaround is needed

D.

Al1 of the above

Full Access
Question # 47

A complex project will fit best in what type of an organization?

A.

Functional

B.

Cross-functional

C.

Matrix

D.

Balanced

Full Access
Question # 48

Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?

A.

6

B.

4

C.

6.3

D.

6.1

Full Access