Searching for workable clues to ace the PMI PMI-002 Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMI-002 PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 41

________ must be measured regularly to identify variance from the plan.

A.

Project performance

B.

Stakeholder requirements

C.

Schedule progress

D.

Cost and schedule

Full Access
Question # 42

The ability of a product to be used for different purposes at different capacities and under different conditions determines its ____________.

A.

Usability

B.

Flexibility

C.

Operability

D.

Availability

Full Access
Question # 43

A structured tool, usually industry or activity specific, used to verify that a set of required steps has been performed is called _________.

A.

Quality Policy

B.

check List

C.

Trenc' Analysis

D.

Paieto Diagram

Full Access
Question # 44

How much time does the typical project manager spend communicating both formally and informally?

A.

40-60%

B.

50-70%

C.

60-80%

D.

75-90%

Full Access
Question # 45

Which process involves coordinating people and other resources to carry out plan?

A.

Executing processes

B.

Planning processes

C.

Controlling Processes

D.

Closing processes

Full Access
Question # 46

A contingency plan is executed when _____________.

A.

A risks is identified

B.

An identified risk occurs

C.

When a workaround is needed

D.

Al1 of the above

Full Access
Question # 47

A complex project will fit best in what type of an organization?

A.

Functional

B.

Cross-functional

C.

Matrix

D.

Balanced

Full Access
Question # 48

Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?

A.

6

B.

4

C.

6.3

D.

6.1