Question # 17

The adjustment of task schedules in order to deploy human resource more effectively is called resource _______.

A.

Tracking

B.

Loading

C.

Crashing

D.

Levelling

Full Access
Question # 18

Ideally, resource levelling should be limited to activities ________.

A.

With negative float

B.

Witn zero float

C.

0n tne critical path

D.

With positive float

Full Access
Question # 19

Cost of quality includes ___________.

A.

Cost of all work to build a product or service that conforms to the requirements

B.

Training programs

C.

Cost of all work resulting from non-conformance to the requirements

D.

Al1 of the above

Full Access
Question # 20

All of the following are communication tools EXCEPT ___________.

A.

Memos

B.

Verbal circulation of a rumour

C.

videos

D.

Inputting data into a spreadsheet

Full Access
Question # 21

The independence of two events in which the occurrence of one is not related to the occurrence of the other is called ________________.

A.

Event phenomenon

B.

Independent probability

C.

Statistical independence

D.

Statistical probability

Full Access
Question # 22

Which of the following processes involves obtaining information (bids and proposals) from prospective sellers?

A.

Procurement Planning

B.

Source Selection

C.

Contract Administration

D.

Solicitation

Full Access
Question # 23

Customer formally accepts the deliverables of each project phase. This process is known as ________.

A.

Verify Scope

B.

Quality Assurance

C.

Quality Control

D.

Quality Measurement

Full Access
Question # 24

Make-or-buy decisions measure the costs of both options. What are the two options?

A.

Direct ar|d Indirect

B.

Tactical and Strategic

C.

Management and Project

D.

0n|y Tactical

Full Access