Searching for workable clues to ace the PMI PMI-002 Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMI-002 PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 17

The adjustment of task schedules in order to deploy human resource more effectively is called resource _______.

A.

Tracking

B.

Loading

C.

Crashing

D.

Levelling

Full Access
Question # 18

Ideally, resource levelling should be limited to activities ________.

A.

With negative float

B.

Witn zero float

C.

0n tne critical path

D.

With positive float

Full Access
Question # 19

Cost of quality includes ___________.

A.

Cost of all work to build a product or service that conforms to the requirements

B.

Training programs

C.

Cost of all work resulting from non-conformance to the requirements

D.

Al1 of the above

Full Access
Question # 20

All of the following are communication tools EXCEPT ___________.

A.

Memos

B.

Verbal circulation of a rumour

C.

videos

D.

Inputting data into a spreadsheet

Full Access
Question # 21

The independence of two events in which the occurrence of one is not related to the occurrence of the other is called ________________.

A.

Event phenomenon

B.

Independent probability

C.

Statistical independence

D.

Statistical probability

Full Access
Question # 22

Which of the following processes involves obtaining information (bids and proposals) from prospective sellers?

A.

Procurement Planning

B.

Source Selection

C.

Contract Administration

D.

Solicitation

Full Access
Question # 23

Customer formally accepts the deliverables of each project phase. This process is known as ________.

A.

Verify Scope

B.

Quality Assurance

C.

Quality Control

D.

Quality Measurement

Full Access
Question # 24

Make-or-buy decisions measure the costs of both options. What are the two options?

A.

Direct ar|d Indirect

B.

Tactical and Strategic

C.

Management and Project

D.

0n|y Tactical

Full Access
Go to page: