Question # 49

What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?

A.

Lots of free float

B.

Idle resources

C.

Negative float

D.

Positive float

Full Access
Question # 50

You are the Project Managers of ABC company. The Project team members are from the finance and accounts. The team members report to Finance and Account Managers respectively, and you have limited control over them. What type of organizational hierarchy does ABC company follow?

A.

Matrix organization

B.

Projectized organization

C.

Functional organization

D.

None

Full Access
Question # 51

A period of time in work weeks which includes non-working days is called:

A.

Elapsed Time

B.

Duration

C.

Effort

D.

Earned Time

Full Access
Question # 52

Which of the following Enterprise Environmental factors are not the inputs for the Develop Human Resource Plan process:

A.

Organizational Chart Tempates

B.

Reduced Training Funds

C.

Hiring Freeze

D.

Technical competencies of project staff

Full Access
Question # 53

Which of the following documents the characteristics of a product or service that the project was undertaken to build.

A.

Resource plan

B.

Project charter

C.

Project description

D.

Scope statement

Full Access
Question # 54

A _______ is a series of actions bringing about a result.

A.

Project plan

B.

Process

C.

Schedule

D.

Flowchart

Full Access
Question # 55

A change requests can occur due to:

A.

An external event such as a change in government regulation.

B.

An error or omission in defining the scope of the product.

C.

An error or omission in defining the scope of the project.

D.

all of the above

Full Access
Question # 56

Your project has a budget of $240,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. The project is now in the fourth month, the work is on schedule, but you have spent $120,000 of the project budget. What is your COST Variance percentage in this case?

A.

-50%

B.

50%

C.

40%

D.

20%

Full Access