Question # 97

Which of the following technique to identify the underlying cause of a problem and take steps to prevent further occurrence?

A.

Root cause analysis

B.

Quality audits

C.

Project audits

D.

Risk audits

Full Access
Question # 98

If a project with a CPI of 0.8, what you tell?

A.

The project is consuming more resources than anticipated.

B.

The project is using fewer resources than anticipated.

C.

The project is falling behind.

D.

The project is running ahead of schedule.

Full Access
Question # 99

You are managing a project that will implement a new Insurance software package. Two project team members have difficulty working together. They come to you, for help resolving the issues. You immediately set up a meeting that includes the functional manager. After the meeting you and the functional manager discuss the issues and agree on a solution. What type of organizational structure you are working in?

A.

Functional

B.

Balanced matrix

C.

Piojectized

D.

Strong Matrix

Full Access
Question # 100

Project Quality Management includes:

A.

Customer satisfaction

B.

Prevention over inspection

C.

Continuous improvement

D.

Al1 of the above

Full Access
Question # 101

Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of:

A.

Enterprise benefits measurement methods when selecting a project

B.

Integral parts of the SOW

C.

Ways to ensure stakeholder commitment

D.

Project selection methods

Full Access
Question # 102

Based on the PMBOK, who is ultimately responsible for the project quality?

A.

Project team

B.

Project manager

C.

QA manager

D.

Validation engineer

Full Access
Question # 103

You are project manager of a project and you are offering an estimate that you know will be changed after the contract is signed is ___________.

A.

Bad practice

B.

Unprofessional practice

C.

Bacl f°r both tne buyer and seller

D.

Al1 of the above

Full Access
Question # 104

Define Scope involves subdividing the major project deliverables into smaller, more manageable components to __________.

A.

Improve the accuracy of cost, time and resource estimates

B.

Define a baseline for performance measurement and control

C.

Facilitate clear responsibility assignments

D.

Al1 of the above

Full Access