Question # 9

Andy is the project manager of the NHGQ project for his organization. He has elected to use a three-point estimate for his project. His project team, however, is complaining about participating in this estimate type because of the time it takes to predict the duration of activities. Andy, as the project manager, tells the project team that they must create the time estimate, as it will help this project and future similar projects. What is a three-point estimate?

A.

Each activity must be estimated for its optimistic, pessimistic, and most likely duration.

B.

Each activity must be estimated for its optimistic, pessimistic, and most likely duration and then an average for the estimate is created.

C.

A three-point estimate, also known as PERT, uses the formula optimistic, plus four times the most likely, plus the pessimistic. This value is then divided by six.

D.

A three-point estimate, also known as GERT, uses the formula optimistic, plus four times the most likely, plus the pessimistic. This value is then divided by six.

Full Access
Question # 10

Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an input to the determine budget process?

A.

Contract

B.

Reserve analysis

C.

Scope baseline

D.

Project schedule

Full Access
Question # 11

George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule. What value should George report in this instance?

A.

.96

B.

-$77,800

C.

$-34,500

D.

-$13,800

Full Access
Question # 12

Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

A.

It is a term used to describe activities whose effort cannot be directly measured to the project objectives.

B.

It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.

C.

It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.

D.

It is a term used to describe activities that are core project management processes, but not core project activities.

Full Access
Question # 13

You are the project manager of the NDF project. You need to determine how often a complete project report can be made, including forecasted project completion information for your project. How often should the report be created?

A.

Weekly

B.

One per status milestone reached

C.

Regularly or on an exception basis

D.

Exception-by-exception basis

Full Access
Question # 14

You are the project manager for your organization. You are discussing an upcoming project with management and they would like you to begin decomposing the project work packages into activities as soon as possible. You have explained to the management that you would like to involve your roject team before the decomposition of the work packages begins. Why would you want your project team to involve in this activity?

A.

To understand the exact type of work the project team will be completing

B.

To help the activity go faster

C.

To get better and more accurate results through the decomposition

D.

To create assignments for the project team as the activities are discussed

Full Access
Question # 15

You are the project manager of the AHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day of early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?

A.

Adding leads to the project work

B.

Fast tracking

C.

Crashing

D.

Using the critical chain method

Full Access
Question # 16

John is the project manager for his organization. He has created a status dashboard for his stakeholders. What is a status dashboard?

A.

It is a report that details the current status of risks and issues.

B.

It is a software application that allows stakeholders to view the project manager's performance.

C.

It is a web-based tool to inspect the project deliverables for performance.

D.

It is a report that reflects the overall performance of scope, schedule, quality, cost, or other project performance metrics.