Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-SP Exam Dumps - PMI Scheduling Professional

Go to page:
Question # 41

You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?

A.

Scope change control

B.

Schedule change control

C.

Integrated change control

D.

Change Control Board approval process

Full Access
Question # 42

You are creating a status report to show how your project is progressing. Management is interested in several key activities and their status. You need to report work performance information to management. All of the following are example of work performance information you should include in your report except for which one?

A.

How the project is performing on its schedule.

B.

Performance of the selected project vendors

C.

Which activities have been started and which activities have been finished.

D.

Percent of completion for the in-progress activities

Full Access
Question # 43

Complete this sentence:

_________________________ is the process of collecting and distributing performance information including status reports, progress measurements, and forecasts.

A.

Corrective action

B.

Report performance

C.

Earned value management

D.

Monitor and control project performance

Full Access
Question # 44

What project management plan will document the time frame and frequency for the distribution of required information?

A.

Scope Management Plan

B.

Communications Management Plan

C.

Stakeholder Management Plan

D.

Schedule Management Plan

Full Access
Question # 45

What is the formula to find the schedule performance index?

A.

EV-PV

B.

EV/AC

C.

EV/PV

D.

EV-AC

Full Access
Question # 46

Your organization wants to start a new project. The study shows that the new project will save organization approximately $200,000 per year. Now it is required to move forward with the project. Which of the following documents will define the project justification?

A.

Feasibility study

B.

Project charter

C.

Work breakdown structure

D.

Project scope

Full Access
Question # 47

You work as a project manager for BlueWell Inc. There have been changes to the project scope in your project. These changes will cause the project schedule to change as well, so you will need to update the schedule and the schedule baseline. The schedule baseline is a component of what?

A.

Project calendar

B.

Project constraints

C.

Project objectives

D.

Project management plan

Full Access
Question # 48

Which of the following statements best describes an activity in a project?

A.

It is a defined set of functions a resource must complete for the project scope to be considered complete.

B.

It is the effort needed to complete a work package.

C.

It is the unit of resource utilization needed to complete a project deliverable.

D.

It is a listing of all project work that must be accomplished for the project scope to be considered complete.

Full Access
Go to page: