Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-SP Exam Dumps - PMI Scheduling Professional

Go to page:
Question # 17

Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?

A.

Diane

B.

Project sponsor

C.

Risk owner

D.

Subject matter expert

Full Access
Question # 18

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

A.

-$135,000

B.

.67

C.

.81

D.

-$65,000

Full Access
Question # 19

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:

Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity D is delayed by two days?

A.

One

B.

Five

C.

Four

D.

Zero

Full Access
Question # 20

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.

A.

Quality inspections and compliance

B.

Location, logistics, and resource availability analysis

C.

Labor productivity studies from previous similar projects in the area

D.

The average price of general labor in the area

Full Access
Question # 21

Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

A.

Archive the project records.

B.

Summarize the project risks costs.

C.

Summarize the project variance.

D.

Close the project office.

Full Access
Question # 22

Your project is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked that you report on the schedule variance for your project. If your project has a BAC of $650,000 and you've spent $385,000 to date, what is the schedule variance value?

A.

-$75,500

B.

-$390,000

C.

-$487,500

D.

-$65,000

Full Access
Question # 23

You are the project manager for your organization. You are working with your project team to create activity duration estimates using the PERT method. What is the formula for PERT?

A.

(O+ML+P)

B.

(O+(6M)+P)6

C.

(O+ML+P)/3

D.

(O+(4M)+P)/6

Full Access
Question # 24

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index?

A.

1.02

B.

0.98

C.

0.90

D.

-$108,120

Full Access
Go to page: