Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-SP Exam Dumps - PMI Scheduling Professional

Go to page:
Question # 4

You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?

A.

Push technique

B.

Many-to-many

C.

One-to-one

D.

Pull technique

Full Access
Question # 5

Which of the following is an output of the Identify Stakeholders process?

A.

Scope baseline

B.

Project scope statement

C.

Project charter

D.

Stakeholder register

Full Access
Question # 6

All of the following statements about the critical path are false except for which one?

A.

The critical path cannot be crashed.

B.

The critical path is the shortest path in the project network diagram.

C.

The critical path is always one path with the longest duration.

D.

The critical path shows the project's earliest date for completion.

Full Access
Question # 7

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your schedule variance for this project?

A.

$11,667

B.

1.02

C.

$7,000

D.

$-111,750

Full Access
Question # 8

Once the project's WBS has been created what process may happen next?

A.

Estimate activity resources

B.

Define activities

C.

Estimate activity durations

D.

Sequence activities

Full Access
Go to page: