Question # 25

You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?

A.

Cost variance report

B.

Exceptions report

C.

Performance management report

D.

Schedule variance report

Full Access
Question # 26

You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?

A.

It means the largest schedule variance you can have is five percent.

B.

It is the earned value divided by the planned value for your project.

C.

It is the expectation of management to be 95 on schedule at 95 percent of the project.

D.

It means you will need to earn at least 95 cents per dollar invested in the project.

Full Access
Question # 27

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is this project's to-complete performance index based on the current BAC?

A.

1.02

B.

0.010

C.

0.75

D.

0.95

Full Access
Question # 28

Ben is the project manager for his organization. His project has 26 stakeholders this week and will have five additional stakeholders next week. How many more communication channels will Ben's project have next week?

A.

140

B.

10

C.

325

D.

5

Full Access
Question # 29

John works as a Project Manager for Blue Well Inc. He is measuring cost efficiency of his project. The key values are provided in the table below:

What is the cost performance index (CPI) of the project at the current point of time?

A.

0.96

B.

1.082

C.

0.833

D.

1.0625

Full Access
Question # 30

You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms. What type of an estimate are you creating in this scenario?

A.

Parametric estimate

B.

Definitive estimate

C.

Analogous estimate

D.

Bottom-up estimate

Full Access
Question # 31

Ben is the project manager of the NHF Project for his organization. Some delays early in the project have caused the project schedule to slip by nearly 15 percent. Management would like Ben to find a method to recoup the schedule slippage and to get the project back on track. Management is risk-adverse with this project. Which of the following methods should Ben avoid to recoup the project time?

A.

Crashing

B.

Fast tracking

C.

Critical chain methodology

D.

Adding lead time

Full Access
Question # 32

You are the project manager for your organization. You need the oak cabinets for your project delivered by December 1 in order to install the floors around the oak cabinets by December 15. Your company's procurement office generally takes 45 days to complete procurement orders. Based on this information, how should you schedule the lead time for the cabinet delivery?

A.

Cabinet procurement December 1, plus 45 days lead time

B.

Cabinet procurement November 15

C.

Cabinet procurement December 1, minus 45 days lead time

D.

Cabinet procurement December 15 minus 45 days lead time

Full Access