Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2024 Version)

Go to page:
Question # 289

A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype

What should the project manager do to accelerate this solution?

A.

Contact the other project team and ask them to organize a demo of the prototype

B.

Perform iterative planning with the team to use the prototype

C.

Check the burnup charts to see what progress has been made to integrate the solution

D.

Prioritize the backlog with the customer to remove the feature

Full Access
Question # 290

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

A.

Develop requirements and designs to support a faster product release.

B.

Emphasize the adoption of a predictive approach to minimize ambiguity.

C.

Recommend an agile approach so the project can be delivered iteratively.

D.

Outsource development of the product to a third party with more experience.

Full Access
Question # 291

A project manager who works for a company involved in several industries is asked

to lead a software development project for a government agency. The company attempted to

execute similar projects for other industries before but was unsuccessful.

What should the project manager do to ensure project success?

A.

Document this information in the risk management plan.

B.

Develop a contingency plan to prepare for possible risks.

C.

Continue executing the project using expert judgment.

D.

Review the lessons learned registers from the previous projects.

Full Access
Question # 292

There is a problem with a project because some features are not in compliance with

regulations. Some stakeholders do not believe compliance is a priority, while others disagree.

What should the project manager do?

A.

Review the stakeholder engagement assessment matrix to determine next steps.

B.

Set up some time with the stakeholders to explain the importance of compliance.

C.

Meet with the sponsor to discuss how to handle the stakeholders' differing opinions.

D.

Send out documentation to align stakeholder expectations and project objectives.

Full Access
Question # 293

A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?

A.

Follow the risk response plan

B.

Use the contingency fund

C.

Prepare a change request

D.

Update the risk register

Full Access
Question # 294

A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?

A.

Stakeholder analysis

B.

Resource needs analysis

C.

Accommodations assessment

D.

Team member assessment

Full Access
Question # 295

A project manager Is working on the initial phases of a highly technical project that employs the "first of its kind" technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and queries raised that are taking the discussions to a different level, and a great deal of time is wasted

What should the project manager do?

A.

Request stakeholders who understand the technology.

B.

Recommend a change in technology to senior management.

C.

Plan to conduct informal sessions with the stakeholders.

D.

Include the issue in the Issue log and escalate to senior management.

Full Access
Question # 296

A project is on its sixth iteration out of seven. Select the two points where the team is

performing better than expected. (Choose two.)

Full Access
Go to page: