Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2024 Version)

Go to page:
Question # 321

On a recently completed prefect a project manager noticed that some of the subcontractors approached the client directly with questions. These subcontractors had a previous direct reporting relationship with the client. The project manager is now in the initial stage of a new project with the same subcontractors and client.

How should the project manager set up communications?

A.

Inform the client that all communications moving forward will go through the project manager

B.

Ensure that the communications management plan covers contractual obligations

C.

Consult the communications management plan from a recent project that has been closed

D.

Update the communications management plan to allow the subcontractors to communicate directly with the client

Full Access
Question # 322

A project sponsor asks the project manager to explore a hybrid approach for a new

project. The product manager for this project has already prepared a detailed specification for the product.

What should the project manager do to proceed with the project management plan?

A.

Ask the team to assess whether the product specification can be expressed in user

stories to enable a Scrum or Kanban approach.

B.

Explore with the product manager to determine if there are viable opportunities to

deliver value incrementally and increase business value.

C.

Recommend to the project sponsor that a predictive approach is appropriate for the

project due to the stable product requirements.

D.

Ask the product manager whether they are prepared to act as product owner for the

project in order to participate in iterative planning and reviews.

Full Access
Question # 323

A team lead has been highly engaged and involved in a project and is operating without a chain of command or authority levels What is the team lead dang1?

A.

Modeling directive leadership

B.

Modeling commanding leadership

C.

Modeling adaptive leadership

D.

Modeling servant leadership

Full Access
Question # 324

A project team consists of members based in country A and subject matter experts

(SMEs) based in country B with a 12-hour time difference. What can the project manager do

to improve interactions between the team members in both countries?

A.

Ensure full participation of both the product owner and business SMEs in scope

planning sessions.

B.

Identify virtual communication methods and arrange for regular team meetings

accordingly.

C.

Explore the opportunity to have both teams colocated.

D.

Plan for frequent face-to-face meetings.

Full Access
Question # 325

A project has been running successfully for 2 months. At a regular project meeting,

the team raises several potential obstacles to future progress. The obstacles include vendor

delivery performance, technical performance of a subsystem, and conflict with another division of the organization.

What should the project manager do next?

A.

Work with the team and others in the network to assess and prioritize the obstacles.

B.

Engage with the external stakeholders and the other division of the organization to

resolve the issues.

C.

Escalate the obstacles to the project sponsor for assistance with resolution.

D.

Determine a change response to identify and resolve the obstacles to move the project

forward.

Full Access
Question # 326

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage

What should the project manager do?

A.

Investigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics

B.

Stop the project and kick off another project to apply alternative wires for the machine

C.

Meet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider

D.

Meet with the wire manufacturer to secure enough of the existing stock for the machine

Full Access
Question # 327

In the planning phase, a project manager receives identified risks from the sponsors

and subject matter experts (SMEs) and wants to develop a risk response strategy for them.

What should the project manager do first?

A.

Perform a risk reserve analysis.

B.

Assign allocated budget to cover key risks.

C.

Agree on the criteria to prioritize risks.

D.

Assign a risk responsibility to each team member.

Full Access
Question # 328

A government agency is developing a new connectivity policy. The assigned project

manager is a famous economist with international recognition. The team is eager to work with

the project manager, but feels intimidated. The project manager realizes that a junior

economist, whose tasks are behind schedule, is especially intimidated by the situation.

What should the project manager do first?

A.

Evaluate the performance of the junior economist in the upcoming months.

B.

Reassign some of the junior economist's tasks to other economists.

C.

Request to replace the junior economist with a more experienced economist.

D.

Consider organizing paired work sessions for the junior and senior economists.

Full Access
Go to page: