Special Summer Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PSM-I Exam Dumps - Professional Scrum Master I

Go to page:
Question # 73

What is the timebox for a Sprint Planning event? (choose the best answer)

A.

Monthly.

B.

8 hours for a one-month Sprint

C.

Whenever ills done

D.

4 hours for a one-month Sprint

Full Access
Question # 74

For which of the following is the Scrum Master responsible?

(choose the best answer)

A.

Properly adopting and using the Scrum framework.

B.

Keeping track of resource allocation.

C.

Managing the performance of the Scrum Team.

D.

The meetings and the objectives that a Scrum Team sets for itself.

Full Access
Question # 75

When is a Product Backlog item considered complete? (choose the best answer)

A.

When the item passes ail acceptance criteria

B.

When the item has gamed product sponsor approval

C.

At the end of the Sprint

D.

When the item meets the Definition of Done

Full Access
Question # 76

Which three of the following are time-boxed events in Scrum? (Choose the best three answers.)

A.

Release Planning.

B.

Release Retrospective.

C.

Sprint Retrospective.

D.

Sprint Planning.

E.

Sprint Testing.

F.

Sprint 0.

G.

Daily Scrum.

Full Access
Question # 77

What is the purpose of a Sprint Review?

A.

To take time to judge the validity of the project.

B.

To inspect the product increment with the stakeholders and collect feedback on next steps.

C.

To review the Scrum Team’s activities and processes during the Sprint.

D.

To build team sprint.

Full Access
Question # 78

When a Development Team is having trouble delivering a working Increment because they don’t understand a functional requirement, what should they do?

A.

Add a specialist to the Development Team.

B.

Partially complete the functionality, and discuss the remaining work at the Sprint Review.

C.

Collaborate with the Product Owner to determine what is possible and acceptable.

D.

Defer the work to a more appropriate Sprint.

Full Access
Question # 79

To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, a Development Team to implement those ideas and a Scrum Master to help guide the process.

A.

True

B.

False

Full Access
Question # 80

Which topics should be discussed in the Sprint Review? (Choose the best answer.)

A.

The Scrum process, and how it was used during the Sprint.

B.

Coding and engineering practices.

C.

The product Increment.

D.

All of the above.

Full Access
Go to page: