Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PSM-I Exam Dumps - Professional Scrum Master I

Go to page:
Question # 9

When does the second Sprint start?

A.

Once the architectural changes for the second Sprint have been approved by the senior architect.

B.

After the Product Backlog for the second Sprint has been selected.

C.

Immediately after the first Sprint.

D.

After the customer completes acceptance testing of the first Sprint.

Full Access
Question # 10

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

A.

The Scrum Team with the highest velocity pulls Product Backlog items first.

B.

The Development Teams pull in work in agreement with the Product Owner.

C.

The Product Owner should provide each team with its own Product Backlog.

D.

Each Scrum Team takes an equal numbers of items.

E.

The Product Owner decides.

Full Access
Question # 11

A new Developer is having continuing conflicts with existing members or the scrum Team, which is impacting the delivery of the Increment It necessary, who is responsible for removing the Developer from the Scrum Team?

(choose the best answer)

A.

The Scrum Master is responsible, they remove impediments

B.

The Product Owner is responsible, they control the return on investment (ROI)

C.

The hiring manager is responsible, they hired the Developer

D.

The Scrum Team is responsible

Full Access
Question # 12

When multiple Scrum Teams are working on the same product, should all of their Increments be

integrated every Sprint? (choose the best answer)

A.

Yes, but only for Scrum Teams whose work has dependencies.

B.

No, that is tar too nard and must be done in a hardening Sprint

C.

No, each Scrum Team stands alone.

D.

Yes, in order to accurately inspect what is done.

Full Access
Question # 13

True or False: A scrum Master Fulfills me same role as a traditional project Manager.

A.

True

B.

False

Full Access
Question # 14

True or False: The Product Owner makes sure the Developers select enough from the Product

Backlog tor a Sprint to satisfy the stakeholders.

A.

True

B.

False

Full Access
Question # 15

Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.

A good way to continue is:

A.

The Development Team makes sure that all of the selected scope per Sprint is as “Done” as possible. The undone work is estimated and added to the Sprint Backlog of the next Sprint, so it doesn’t mess up the Product Backlog.

B.

Add enough people to the Development Team for the deadline to be made.

C.

The opportunity to inspect and adapt is lost. Opaqueness has replaced transparency. Predictability has dropped below zero. The produced software is not usable. As the rules of Scrum have not been respected, it is the Scrum Master’s duty to assess whether repair is possible, or a restart with a more reliable team. If not, the Scrum Master should cancel the project.

D.

The Development Team should remind Marian to find funding for enough Release Sprints in which the remaining work can be done.

Full Access
Question # 16

What happens if the Development Team cannot complete its work by the end of the Sprint?

A.

The Sprint is extended and future Sprints use this new duration.

B.

The Sprint length holds and the Development Team continuously learns what is actually possible to do within a Sprint of this length.

C.

The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.

Full Access
Go to page: