Special Summer Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PSM-I Exam Dumps - Professional Scrum Master I

Go to page:
Question # 49

The Product Backlog is ordered by:

A.

The Product Owner with the most valuable items placed at the top.

B.

Risk, where safer items are at the top, and riskier items are at the bottom.

C.

Items are randomly arranged.

D.

Size, where small items ale at the top and large items are at the bottom.

Full Access
Question # 50

Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.

A good way to continue is:

A.

The Development Team makes sure that all of the selected scope per Sprint is as “Done” as possible. The undone work is estimated and added to the Sprint Backlog of the next Sprint, so it doesn’t mess up the Product Backlog.

B.

Add enough people to the Development Team for the deadline to be made.

C.

The opportunity to inspect and adapt is lost. Opaqueness has replaced transparency. Predictability has dropped below zero. The produced software is not usable. As the rules of Scrum have not been respected, it is the Scrum Master’s duty to assess whether repair is possible, or a restart with a more reliable team. If not, the Scrum Master should cancel the project.

D.

The Development Team should remind Marian to find funding for enough Release Sprints in which the remaining work can be done.

Full Access
Question # 51

For which is the Scrum Master responsible?

A.

Managing the performance of the Scrum Team.

B.

The meetings and the objectives that a Scrum Team sets for itself.

C.

The Scrum framework being adopted and used properly.

D.

Keeping track of resource allocation.

Full Access
Question # 52

You have just been hired by a company new to Scrum. Your management has assigned you to

be the Scrum Master of six new Scrum Teams. These teams will build one product Select two

conditions you should strive tor in this scenario.

(choose the best two answers)

A.

There should be six Product Owners, one tor each Scrum Team.

B.

There should be six Product Owners, reporting to a Chief Product Owner.

C.

The product has one Product Backlog.

D.

Each Scrum Team should have a separate Product Backlog.

E.

There should be only one Product Owner.

Full Access
Question # 53

A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items “Done” by the end of the Sprint. Which three phrases best describe the purpose of a definition of “Done”? (Choose three.)

A.

It controls whether the developers have performed their tasks.

B.

It provides a template for elements that need to be included in the technical documentation.

C.

It creates transparency over the work inspected at the Sprint Review.

D.

It trucks the percent completeness of a Product Backlog item.

E.

It guides the Development Team is creating a forecast at the Sprint Planning.

F.

It defines what it takes for an Increment to be ready for release.

Full Access
Question # 54

Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog.

A.

True

B.

False

Full Access
Question # 55

When Goes a Developer become accountable for the value 01 a Product BacKlog item selected for the Sprint'

(choose the best answer)

A.

Never The entire Scrum Team is accountable for creating value every Sprint.

B.

At the Sprint Planning Evented

C.

Whenever a team member can accommodate more worn.

D.

During the Daily scrum

Full Access
Question # 56

What is the recommended size for a Scrum Team? (Choose the best answer.)

A.

At least 7.

B.

9

C.

10 or fewer.

D.

7 plus or minus 3.

Full Access
Go to page: