Question # 41

What is a Development Team responsible for? (Choose two.)

A.

Resolving internal team conflicts.

B.

Reporting productivity.

C.

Selecting the Product Owner.

D.

Organizing the work required to meet the Sprint Goal.

Full Access
Question # 42

If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?

A.

Its productivity is likely to decrease.

B.

Its productivity is likely to stay the same.

C.

Its productivity is likely to increase.

Full Access
Question # 43

A new developer is having continuing conflicts with existing Development Team members and creating the hostile environment. If necessary, who is responsible for removing the team member?

A.

The hiring manager is responsible, because he/she hired the developer.

B.

The Scrum Manager is responsible, because he/she removes Impediments.

C.

The Development Team is responsible, and may need help from the Scrum Master.

D.

The Product Owner is responsible, because he/she controls the return on investment (ROI).

Full Access
Question # 44

Choose two responsibilities of a self-organizing Development Team. (Choose two.)

A.

Reorder the Product Backlog.

B.

Pull Product Backlog items for the Sprint.

C.

Do the work planned in the Sprint Backlog.

D.

Increase velocity.

E.

Report daily progress to stakeholders.

Full Access
Question # 45

Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)

A.

Identifying high priority process improvements for the next Sprint.

B.

The order of items in the Product Backlog.

C.

How the team collaborates.

D.

Documenting acceptance criteria for items in the next Sprint.

Full Access
Question # 46

The Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders.

A.

True

B.

False

Full Access
Question # 47

Which are appropriate topics for discussion in a Sprint Retrospective? (Choose the best three answers.)

A.

Arranging the Sprint Backlog for the next Sprint.

B.

The value of work currently represented in the Product Backlog.

C.

Team relations

D.

Definition of Done.

E.

How the Scrum Team does its work.

Full Access
Question # 48

What are two ways that regulatory compliance issues are dealt with in Scrum?

(choose the best two answers)

A.

They are addressed by a separate team who is responsible for compliance

issues.

B.

They are addressed along with functional development of the product.

C.

They are discussed, determined, and documented before the actual feature

development Sprints.

D.

They are added to the Product Backlog and addressed in early Sprints, while

always requiring at least some business functionality, no matter how small.

Full Access