Question # 25

Stakeholder satisfaction should be managed as a key project:

A.

Benefit

B.

Initiative

C.

Objective

D.

Process

Full Access
Question # 26

An output of the Manage Stakeholder Engagement process is:

A.

change requests

B.

enterprise environmental factors

C.

the stakeholder management plan

D.

the change log

Full Access
Question # 27

What are the Project Procurement Management processes?

A.

Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements

B.

Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements

C.

Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements

D.

Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Full Access
Question # 28

Which item is a formal proposal to modify any document, deliverable, or baseline?

A.

Change request

B.

Requirements documentation

C.

Scope baseline

D.

Risk urgency assessment

Full Access
Question # 29

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

Budget at completion (BAC)

D.

Variance at completion (VAC)

Full Access
Question # 30

Which Process Group and Knowledge Area include the Sequence Activities process?

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

Full Access
Question # 31

Plan Schedule Management is a process in which Knowledge Area?

A.

Project Scope Management

B.

Project Human Resource Management

C.

Project Integration Management

D.

Project Time Management

Full Access
Question # 32

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

A.

0.50

B.

0.67

C.

1.50

D.

2.00

Full Access