Question # 33

Which tool or technique is used in the Perform Integrated Change Control process?

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Full Access
Question # 34

A regression line is used to estimate:

A.

Whether or not a process is stable or has predictable performance.

B.

How a change to the independent variable influences the value of the dependent variable.

C.

The upper and lower specification limits on a control chart.

D.

The central tendency, dispersion, and shape of a statistical distribution.

Full Access
Question # 35

Which document describes the necessary information to determine if a project is worth the required investment?

A.

Cost baseline

B.

Service level agreement

C.

Memorandum of understanding

D.

Business case

Full Access
Question # 36

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Full Access
Question # 37

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

A.

Develop Project Team.

B.

Manage Project Team.

C.

Acquire Project Team.

D.

Plan Human Resource Management.

Full Access
Question # 38

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

A.

Supportive

B.

Directive

C.

Controlling

D.

Instructive

Full Access
Question # 39

Which tool or technique is used in the Estimate Costs process?

A.

Acquisition

B.

Earned value management

C.

Vendor bid analysis

D.

Forecasting

Full Access
Question # 40

The process of identifying and documenting relationships among the project activities is known as:

A.

Control Schedule.

B.

Sequence Activities.

C.

Define Activities.

D.

Develop Schedule.

Full Access