Question # 105

A change to support a regulatory requirement is proposed for inclusion in the scope of a project. A business analyst (BA) conducts an impact analysis to determine the extent of the change. What previous task could assist the BA in performing the impact analysis?

A.

Update use case scenarios

B.

Perform a risk analysis

C.

Create requirement relationships

D.

Conduct a cost-benefit analysis

Full Access
Question # 106

A finance manager wants to begin a new project to replace the existing expenses processing system. The finance manager feels that the current expense submission-to-reimbursement process takes too long and is substantiated by 50% more complaints regarding incorrect reimbursement amounts than the same time last year. What should the business analyst (BA) investigate first?

A.

Submission processes to determine which activities can be fully automated

B.

Business process to uncover inefficiencies and falling control points

C.

Enterprise information model to ensure definitions are still valid

D.

Finance solution vendors for inclusion in a Request for information

Full Access
Question # 107

The business analyst (BA) is helping the business stakeholders prioritize requirements for a new customer portal for managing orders, delivery, and payment information. A number of requirements address compliance with regulations regarding access for people with disabilities. What factor should the BA use to guide the stakeholders when assigning a priority for these specific requirements?

A.

Dependencies

B.

Penalties

C.

Risk

D.

Stability

Full Access
Question # 108

A business analyst (BA) is negotiating and resolving conflict with stakeholders to ensure they participate in the required BA activities. Which element of stakeholder management is the BA performing?

A.

Confirm elicitation results

B.

Gain agreement on commitments

C.

Monitor stakeholder engagement

D.

Plan stakeholder engagement

Full Access
Question # 109

The Chief Executive Officer (CEO) of a company presents a new corporate strategy that will introduce a new system to the organization. The CEO has expressed a concern about the impact to the staff once the strategy has been implemented. What must the business analyst (BA) do to address concerns of the CEO?

A.

Identify required cultural changes

B.

Perform a cost-benefit analysis of the strategy

C.

Ensure requirements are easily accessible

D.

Align the new capabilities to the company's architecture

Full Access
Question # 110

A project team needs to maintain the traceability of requirements for a software system. Due to the large number of requirements, which of the following methods should the team use?

A.

Use a requirements management tool

B.

Create a requirements mode

C.

Maintain the requirements manually

D.

Develop a database management system

Full Access
Question # 111

A business analyst (BA) wants to check the completeness of requirements defined after meeting with project stakeholders. A group of subject matter experts (SMEs) has been identified and invited to a workshop to walk through the requirements. What must the BA do to ensure a shared understanding of requirements?

A.

Align requirements to the organizational strategy

B.

Prioritize requirements according to expected stakeholders value

C.

Ensure requirements attributes are consistent for ease of access

D.

Determine the format to present the requirements to the SMEs attending the workshop

Full Access
Question # 112

An organization has hired a consulting firm to implement and customize a software solution they purchased. The firm has raised concerns regarding the effort required to develop a solution that meets all requirements. On what basis should the requirements be prioritized in this context?

A.

Benefit

B.

Cost

C.

Risk

D.

Penalty

Full Access