A new product that is tablet-enabled is being considered to replace an older product to process orders. The data captured is sent to existing downstream applications, which are not being updated. What is the first thing that a business analyst (BA) should consider?
A business analyst (BA) develops a template to document the product feature requirements for an enterprise software solution. Within the template, the BA includes the following additional information: source, priority level, level of complexity, and last modified date. What does the additional information describe?
A finance manager wants to begin a new project to replace the existing expense processing system. The finance manager feels that the current expense submission-to-reimbursement process takes too long and is substantiated by 50% more complaints regarding incorrect reimbursement amounts than the same time last year. What should the business analyst (BA) investigate first?
A company has bought a customizable software product, and the vendor's business analyst (BA) is visiting the company's office to perform a requirements assessment. The business sponsor expresses an interest in improving a specific process that is in scope. What should the BA do?
An organization's Business Analysis Center of Excellence (BACoE) has deployed several business analysts (BAs) to provide business analysis to a cross-functional initiative. After the first phase of the project, the BACoE seeks to determine the effectiveness of the businessanalysis work. Which of the following techniques could be used to elicit feedback from all affected stakeholders?
A business analyst (BA) is examining the relationships between elicited requirements on a project. What quality criteria must be satisfied when the BA is defining requirements relationships?
System designers are working with a business analyst (BA) during the initial stages of a project to implement a new transaction-based system. The system designers would like to have a visual that illustrates the type of information that will be input into the system, the processes it will support, and the location where it will be stored. What type of diagram meets the designers' needs?
A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are causing the missed milestones. What tool will help address the project manager's concern?