Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CCP Exam Dumps - Certified Cost Professional (CCP) Exam

Go to page:
Question # 49

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following methods a used for creating critical path schedules:

A.

Precedence diagram method

B.

Precedence and arrow diagram methods only

C.

Gantt chart (bar chart) method

D.

Arrow diagram method

Full Access
Question # 50

When a person hears the words being said to him/her, but does not receive the message of the words, it is called

A.

Reflective listening

B.

Judgmental listening

C.

Passive listening

D.

Directive listening

Full Access
Question # 51

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What class of estimate is used for the preliminary design phase of a project?

A.

Class 5 - order of magnitude estimate with +50% / -30% accuracy

B.

Class 1 - order of magnitude with +30% / -30% accuracy

C.

Class 4 - budget estimate with +30% / -15% accuracy

D.

Class 2 - definitive estimate with +15%/-5% accuracy

Full Access
Question # 52

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

An unbalanced bid methodology can best be used by:

A.

Engineer/contractor working for the owner (Plan B)

B.

Subcontractor working for contractor (Plan A or B)

C.

Contractor working directly for engineer (plan A or B)

D.

Engineer working for the owner (Plan A)

Full Access
Question # 53

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If the owner in A has a primary goal of completion within budget, the following contract types with the engineer/contractor would be best:

A.

Engineer — cost plus, contractor fixed price

B.

Engineer — cost plus, contractor cost plus

C.

Engineer fixed price, contactor cost plus

D.

Engineer — fixed price, contractor fixed price

Full Access
Question # 54

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.

Calculate the weighted average unit cost.

A.

$46.13

B.

$47.63

C.

$48.35

D.

$48.09

Full Access
Question # 55

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The return on investment at the end of the fifth year would be:

A.

Greater than 10%

B.

Unknown

C.

Equal to 10%

D.

Less than 10%

Full Access
Question # 56

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Costs which are independent of the system throughout are:

A.

no answers ate correct

B.

both fixed and variable costs

C.

variable costs fixed costs

D.

fixed costs

Full Access
Go to page: