Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CCP Exam Dumps - Certified Cost Professional (CCP) Exam

Go to page:
Question # 41

A bond that guarantees the bidder will enter into a contract on the basis of his/her bid is referred to as:

A.

Surety bond

B.

Performance bond

C.

Bid bond

D.

Liability bond

Full Access
Question # 42

How can the quality of a cost/capacity factor estimate be improved?

A.

Validate the capacity factor from similar, recently completed projects

B.

Validate law productivity from recently completed projects

C.

Verify the labor rates used in the estimate

D.

Verify the equipment costs used in the estimate

Full Access
Question # 43

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If the owner in B has as his primary goal to get the project completed and on line as fast as possible, then he would most likely use the ______________type of contract.

A.

Cost plus

B.

Lump sum

C.

Unit Rate

D.

Lump sum + incentive

Full Access
Question # 44

A project's data shows the budgeted cost of work scheduled as $27,000 and the actual cost of work performed as $25,000. If the baseline budget is $200,000 and the work o-ogress is 12%. what is the cost performance index (CPI)?

A.

1

B.

1.04

C.

0.89

D.

0.96

Full Access
Question # 45

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

According to Maslow's hierarchy of needs, which level should be satisfied first?

A.

Physiological

B.

Self-actualization

C.

Safety needs

D.

Ego-status

Full Access
Question # 46

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Five years from now it is required the company have $100,000. How much money should be invested at the end of each year to reach this?

A.

$15,937

B.

$15,397

C.

$16,380

D.

$13,168

Full Access
Question # 47

A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:

The following question requires your selection of Scenario 1.4.162 from the right side of your split screen, using the drop down menu, to reference during your response/choice of response.

The budgeted cost work performed is;

A.

$90,000

B.

$100,000

C.

$95,000

D.

$108,000

Full Access
Question # 48

You are analyzing historic unit costs for 18'' Class 5 reinforced concrete pipe is a database. The unit costs include all costs-material, labor, equipment, and other, for the excavation, bedding, pipe and backfill. Refer to the following table:

What is the median unit cost?

A.

$48.22

B.

$48.35

C.

$40.00

D.

$46.59

Full Access
Go to page: