11.11 Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

CCP Exam Dumps - Certified Cost Professional (CCP) Exam

Question # 4

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

The following question requires your selection el Scenario 1.4.150 from the right side of your split screen. using the drop down menu to reference during your response/choice of responses.

Based on your analysis, should the press be purchased?

A.

CR is not a factor in this decision

B.

Not enough data to determine

C.

No

D.

Yes

Full Access
Question # 5

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?

A.

Recalculate the early finish for each activity

B.

Recalculate the early start for each activity

C.

Update the remaining duration for each activity

D.

Recalculate the critical path

Full Access
Question # 6

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

The entire pipe has been received, hangers have been installed, and all pipes are in place. None has been welded or flushed. What percent complete is this project?

A.

45%

B.

50%

C.

95%

D.

30%

Full Access
Question # 7

The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

A.

Total float

B.

Remaining duration

C.

Free float

D.

Just-in-time scheduling

Full Access
Question # 8

SCENARIO: A can manufacturing company requested you to provide data for their decision making The unit prices of the can varies but an average selling price of $0.55 cents and average cost of S45 cents is estimated.

The monthly fixed costs are:

Rant-$1,500

Wages - $4.000

Miscellaneous fixed expenses - $500

If the rent increases by 100% and the unit sales/other costs remain unchanged, the new break even amount is?

A.

$60,000

B.

$41,250

C.

$33,000

Full Access
Question # 9

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

In the A relationship, the subcontractor might use an unbalance bid to:

A.

To get more payment early in the job

B.

Decrease the chances of extended claim litigation

C.

Reduce the risk of quantities being greater than estimated

D.

Provides an alternative to competitive bidding

Full Access
Question # 10

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current schedule performance index (SPI)?

A.

0.96

B.

0.88

C.

0.84

D.

1.14

Full Access
Question # 11

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is a method for figuring estimate at completion (EAC)?

A.

BCWP + (BAG - ACWP)

B.

ACWP + (BAC - BCWS)

C.

BCWS + (BAG -ACWP)

D.

ACWP + (BAC - BCWP)

Full Access
Question # 12

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

If $50 was invested at 6.0% on January 1, year 1, what would be the value of year-end withdrawals made in equal amounts each year for 10 years and leaving nothing in the fund after the tenth withdrawal?

A.

$6.80

B.

$3.10

C.

$5.35

D.

$2.22

Full Access
Question # 13

If a project is said to be on a "fast track program/' the fast track method is:

A.

Simultaneous working engineering, procurement, and construction, with appropriate overlap from each phase of work so that delays are eliminated and all the work is streamlined into a correct plan of logic/sequence and duration for all of the work

B.

First completing engineering and procurement, then executing construction

C.

Analyzing the project and specifying the basic approach to be used in its execution; segmenting the project into reasonable number of activities; estimating the time required to perform each activity; placing the activities in time order, considering both sequential and parallel performance

D.

Revising the schedule logic to make it possible to identify constraints of faulty logic; revising the durations in the n p schedule that have been based on assumptions regarding the \hay the work would be performed; revise the resources to work multiple shifts; evaluate the use of overtime

Full Access
Question # 14

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If $20,000 is invested at the end of each fiscal year for the next 10 years, how much would our total investment be worth assuming the interest is at 10%?

A.

$289,370

B.

$318,740

C.

$265,798

D.

$420,236

Full Access
Question # 15

The following question requires your selection of Scenario 1.4.150 from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Annual depreciation (in USS) would be calculated as follows for a capital recovery with salvage analysis:

A.

5,343 par year

B.

4,343 pet year

C.

8,0X10 per year

D.

7,000 per year

Full Access
Question # 16

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

If you buy a lot for $3,000 and sell it for $6,000 at the end of 8 years, what is your annual rate of return?

A.

10.4%

B.

9.1%

C.

8.3%

D.

9.9%

Full Access
Question # 17

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is 1.03. How many hours were planned?

A.

10,586

B.

9,280

C.

9,559

D.

10,278

Full Access
Question # 18

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

Which of the following should be included in the life-cycle cost analysis of a power plant?

A.

Construction cost, operating cost, maintenance cost

B.

Factory expenses, distribution expenses, mark-up

C.

Capacity factor, end product units, physical dimensions

D.

Resources, work activities, final cost objects

Full Access
Question # 19

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.

What is the range of unit costs?

A.

$21.57

B.

$26.65

C.

$48.22

D.

$485.00

Full Access
Question # 20

refers to the process of calculating and reporting the non-monetary functions of the strategic asset portfolio.

A.

Asset performance assessment

B.

Asset project reporting

C.

Asset investment decision and funding

D.

Asset performance measurement

Full Access
Question # 21

A systematic coding structure for organizing and managing scope, assets, cost, resources, work and schedule activity information is a______________.

A.

Cost breakdown structure

B.

Code of accounts

C.

Cost estimate classification

D.

Schedule identification number

Full Access
Question # 22

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26(2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Select the statement that best describes the meaning of the +/-notations associated with an estimate. The actual cost is expected:

A.

To be exactly the percentages stated

B.

To fall within the percentage range stated

C.

To be higher or lower that the percentages stated

D.

To be outside the percentages stated

Full Access
Question # 23

A work breakdown structure (WBS) is developed because:

A.

It avoids omissions of key product activities through a systematic planning process; removes the complexity of the project by dividing it into manageable units; and provides a framework.

B.

It defines specific tasks within a project from which schedules can be developed; it aids in linking activities with resources; it facilitates communication; and it allows integration of project plans

C.

It can be illustrated by individual bars for major phases, such as permitting, funding, engineering, procurement construction, commission/startup

D.

It can be illustrated by a simple bar, with important milestones represented by symbols at the planned time of occurrence

Full Access
Question # 24

The discount rate is a measure used to convert cash flow streams occurring to different points in time to a common base called the net present worth. What is the discount rate based upon?

A.

Inflation and interest rates

B.

The interest rate which the client will have to pay on his loan

C.

Bank rate

D.

The rate of inflation

Full Access
Question # 25

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is the cost performance index (CPI)?

A.

BCWP/ACWP = 105.000/110.000 = 0.95

B.

ACWP/BCWP = 110.000/105,000 = 1.05

C.

BCWS/ACWP = 100.000/110.000-0 91

D.

ACWP/BCWS = 110,000/100.000- 1.10

Full Access
Question # 26

If you deposit $100 per month for two (2) years and earn interest at 12% APR (Annual Percentage Rate) compounded monthly, how much will you have at the end of the period?

A.

$2,424

B.

$2,976

C.

$2,688

D.

$2,697

Full Access
Question # 27

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is 1.03. How many hours have been earned?

A.

9,979

B.

10,586

C.

11,052

D.

9,559

Full Access
Question # 28

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Fred Fiedler's contingency model suggests that:

A.

Leadership styles are just the opposite of the managerial grid model

B.

Successful leadership depends upon a good match

C.

between the style of the leader and the demands of the situation

D.

Successful leadership can always be imposed by experienced supervision

E.

A relationship oriented leader described the least preferred worker in an unfavorable light

Full Access
Question # 29

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following percent complete measurement techniques is best suited for long-term non-production accounts (such as overhead accounts)?

A.

Ratio/level of effort

B.

Start/finish

C.

Units completed

D.

Incremental milestone

Full Access
Question # 30

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the cost of manufacturing labor for the piece of equipment today?

A.

$140,000

B.

$875,000

C.

$210,000

D.

$105,000

Full Access
Question # 31

Which of the following is NOT an advantage specific to a cost reimbursable contract?

A.

Evaluation of proposals are much simpler

B.

Provides flexibility in dealing with changes

C.

An early start can be made

D.

Owner controls all aspects of the work

Full Access
Question # 32

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the "book value (BV) of the asset at the end of 5 years?

A.

$64,000

B.

$16,000

C.

$3,200

D.

$60,000

Full Access
Question # 33

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Profits that could not be formally recognized during a specific financial accounting period because the goods and services did not satisfy all the customer's requirements are:

A.

Marginal profits

B.

Lost profits

C.

Incurred profits

D.

Postponed profits

Full Access
Question # 34

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of 30 months, copper prices will have increased by what percentage over today's price?

A.

4.6%

B.

3.5%

C.

6.6%

D.

2.5%

Full Access
Question # 35

You have been hired as the cost engineer for a mechanical contractor and have been provided the following information:

What is the schedule performance index (SPI)?

A.

ACWP/BCWS= 110,000/100,000= 1.10

B.

BCWS/ACWP = 100,000/110,000 = 0.91

C.

BCWP/BCWS = 105,000/100,000- 1.05

D.

BCWS/BCWP= 100,000/105,000-0.95

Full Access
Question # 36

Which of the following is NOT an aspect of quality management?

A.

Quality assurance

B.

Quality planning

C.

Quality checking

D.

Quality control

Full Access
Question # 37

An owner advertised his villa for sale. An investor worked out an estimate on the basis mat the villa could be rented out for $1000 per month. Maintenance charges and other taxes are estimated to be $1,500 per year. The tenant has to pay all utility charges. The investor thinks that he can sell this villa for S100.000 alter 6 years. Assuming that the minimum acceptable rate of return is 12%. answer the following question.

The villa could be recommended for purchase at all of the below-mentioned prices except:

A.

$94,500

B.

$92.800

C.

$90,5000

D.

$93,500

Full Access
Question # 38

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

What Kind of optimization modeling is used in making investment analysis to evaluate the risks associated with the potential investment?

A.

Linear Probability Model

B.

Business Modeling

C.

Five-stop Regression Model

D.

Monte Carlo Simulation

Full Access
Question # 39

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

The equivalent value of an investment alternative in today's dollars is referred to as the:

A.

Break-even point

B.

Rate of return

C.

Net present worm

D.

Future value

Full Access
Question # 40

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

If XYZ considers S550 per month the minimum acceptable net income, the number of units that will have to be sold is:

A.

65,500 units

B.

50,000 units

C.

40,000 units

D.

60,000 units

Full Access
Question # 41

A bond that guarantees the bidder will enter into a contract on the basis of his/her bid is referred to as:

A.

Surety bond

B.

Performance bond

C.

Bid bond

D.

Liability bond

Full Access
Question # 42

How can the quality of a cost/capacity factor estimate be improved?

A.

Validate the capacity factor from similar, recently completed projects

B.

Validate law productivity from recently completed projects

C.

Verify the labor rates used in the estimate

D.

Verify the equipment costs used in the estimate

Full Access
Question # 43

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If the owner in B has as his primary goal to get the project completed and on line as fast as possible, then he would most likely use the ______________type of contract.

A.

Cost plus

B.

Lump sum

C.

Unit Rate

D.

Lump sum + incentive

Full Access
Question # 44

A project's data shows the budgeted cost of work scheduled as $27,000 and the actual cost of work performed as $25,000. If the baseline budget is $200,000 and the work o-ogress is 12%. what is the cost performance index (CPI)?

A.

1

B.

1.04

C.

0.89

D.

0.96

Full Access
Question # 45

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

According to Maslow's hierarchy of needs, which level should be satisfied first?

A.

Physiological

B.

Self-actualization

C.

Safety needs

D.

Ego-status

Full Access
Question # 46

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Five years from now it is required the company have $100,000. How much money should be invested at the end of each year to reach this?

A.

$15,937

B.

$15,397

C.

$16,380

D.

$13,168

Full Access
Question # 47

A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:

The following question requires your selection of Scenario 1.4.162 from the right side of your split screen, using the drop down menu, to reference during your response/choice of response.

The budgeted cost work performed is;

A.

$90,000

B.

$100,000

C.

$95,000

D.

$108,000

Full Access
Question # 48

You are analyzing historic unit costs for 18'' Class 5 reinforced concrete pipe is a database. The unit costs include all costs-material, labor, equipment, and other, for the excavation, bedding, pipe and backfill. Refer to the following table:

What is the median unit cost?

A.

$48.22

B.

$48.35

C.

$40.00

D.

$46.59

Full Access
Question # 49

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following methods a used for creating critical path schedules:

A.

Precedence diagram method

B.

Precedence and arrow diagram methods only

C.

Gantt chart (bar chart) method

D.

Arrow diagram method

Full Access
Question # 50

When a person hears the words being said to him/her, but does not receive the message of the words, it is called

A.

Reflective listening

B.

Judgmental listening

C.

Passive listening

D.

Directive listening

Full Access
Question # 51

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What class of estimate is used for the preliminary design phase of a project?

A.

Class 5 - order of magnitude estimate with +50% / -30% accuracy

B.

Class 1 - order of magnitude with +30% / -30% accuracy

C.

Class 4 - budget estimate with +30% / -15% accuracy

D.

Class 2 - definitive estimate with +15%/-5% accuracy

Full Access
Question # 52

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

An unbalanced bid methodology can best be used by:

A.

Engineer/contractor working for the owner (Plan B)

B.

Subcontractor working for contractor (Plan A or B)

C.

Contractor working directly for engineer (plan A or B)

D.

Engineer working for the owner (Plan A)

Full Access
Question # 53

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If the owner in A has a primary goal of completion within budget, the following contract types with the engineer/contractor would be best:

A.

Engineer — cost plus, contractor fixed price

B.

Engineer — cost plus, contractor cost plus

C.

Engineer fixed price, contactor cost plus

D.

Engineer — fixed price, contractor fixed price

Full Access
Question # 54

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.

Calculate the weighted average unit cost.

A.

$46.13

B.

$47.63

C.

$48.35

D.

$48.09

Full Access
Question # 55

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The return on investment at the end of the fifth year would be:

A.

Greater than 10%

B.

Unknown

C.

Equal to 10%

D.

Less than 10%

Full Access
Question # 56

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Costs which are independent of the system throughout are:

A.

no answers ate correct

B.

both fixed and variable costs

C.

variable costs fixed costs

D.

fixed costs

Full Access