Question # 17

A milestone task on the critical path has been completed.

Which of the following should the project manager notify?

A.

Owner of predecessor task

B.

Project team

C.

Project sponsor

D.

Project steering committee

Full Access
Question # 18

An industry leader may be joining the project team and can potentially provide additional expertise. Which of the following strategies should the project manager employ?

A.

Exploitation

B.

Acceptance

C.

Validation

D.

Transfer

Full Access
Question # 19

When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?

A.

Issue log

B.

Risk management plan

C.

Communications plan

D.

Risk register

E.

Status report

Full Access
Question # 20

Project team members have stated that they are having difficulty reaching the newly available corporate resources, and any response comes at unusual hours. Which of the following is MOST likely the cause?

A.

Merger

B.

Relocation

C.

Offshoring

D.

Outsourcing

Full Access
Question # 21

Which of the following is a component of the project cost control?

A.

Scope statement

B.

Burn rate

C.

MOU

D.

SLA

Full Access
Question # 22

Prior to engaging a vendor on an RFI, which of the following documents protects the company's interests?

A.

NDA

B.

SLA

C.

MOU

D.

LOI

Full Access
Question # 23

During a project, the purpose of examining the cost baseline is to:

A.

organize payment of the bills

B.

determine the minimal cost of the project

C.

anticipate the total planned costs

D.

compare against the total planned income

Full Access
Question # 24

A project sponsor has repeatedly indicated dissatisfaction with the resjits o' several projects being managed by different individuals and consisting of different teams within the organization. Which of the following is the best action for management to take NEXT?

A.

Change to a matrix organizational structure.

B.

Audit the project management process.

C.

Enforce the use of EVM.

D.

Remove the project sponsor.