Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PK0-004 Exam Dumps - CompTIA Project +

Go to page:
Question # 65

A project manager determines deliverables are not meeting customer specifications. During which of the

following project phases is this determination MOST likely to happen?

A.

Monitor and control

B.

Execution

C.

Closing

D.

Planning

Full Access
Question # 66

A PM is reviewing bids from vendors and has a question.

Which of the following documents should the PM use to obtain a response?

A.

Project schedule

B.

RFP

C.

Quotation

D.

RFI

Full Access
Question # 67

A project manager is meeting with top management executives and presenting a project status report. The Chief Information Officer (CIO) and other executives complain that the meeting is taking too long and not providing summary information on the project’s progress.

Which of the following should the project manager be presenting?

A.

Project issue

B.

Project dashboard

C.

Project schedule

D.

Project milestone

Full Access
Question # 68

A Chief Executive Officer (CEO) has approached a project team member to request a project change.

Which of the following would be the BEST step for the project manager to take to prevent scope creep?

A.

Deny the CEO’s request.

B.

Implement the project change.

C.

Submit the request to the CCB.

D.

Ask the CEO to follow the communications plan.

Full Access
Question # 69

A project manager is overseeing a multinational project, and team leaders from numerous countries indicate the team members have low morale.

Which of the following is the MOST likely reason the project manager would be unaware of the team member’s decreased morale?

A.

The project manager did not pay attention to visual cues.

B.

The project manager did not perform active listening.

C.

The project manager did not prioritize team member concerns.

D.

The project manager did not visit the project’s international office locations.

Full Access
Question # 70

A project manager is not required to participate in performance appraisal meetings with team members. The project manager is working within which of the following organizational structures?

A.

Projectized

B.

Balanced matrix

C.

Functional

D.

Strong matrix

Full Access
Question # 71

Which of the following will identify the MOST potential project risks?

A.

Cost-benefit analysis

B.

Past project documentation

C.

Project budget

D.

Benchmarking

Full Access
Question # 72

An organization wants assurance that the specialty tools necessary for operation will function as intended for a

specific minimum time period. Which of the following documents BEST provides this assurance?

A.

Purchase order

B.

Non-disclosure agreement

C.

Request for proposal

D.

Warranty

E.

Service level agreement

Full Access
Go to page: