Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PK0-004 Exam Dumps - CompTIA Project +

Go to page:
Question # 81

The government wants to start a project that will launch a satellite but lacks the appropriate SMEs. Which of the following would be BEST to solicit vendors?

A.

LOI

B.

RFQ

C.

RFI

D.

SOW

Full Access
Question # 82

The responsibility of estimating how long a task will take belongs to the:

A.

project scheduler

B.

project team

C.

project manager

D.

project coordinator

Full Access
Question # 83

A project is due to deliver, configure, and install a collection of medical devices. The first device in the collection is reportedly four weeks behind schedule is manufacturing. Which of the following BEST describes how the project manager can keep the project on track?

A.

Expedite shipping of the first item to keep the installation order.

B.

Rearrange the installation dates since other devices are already on site.

C.

When the late equipment arrives, have the team work overtime.

D.

Explain the vendor payments will be withheld if delivery is not met.

Full Access
Question # 84

Team members in a projectized organization are released at the end of a project and placed on the “bench”. Which of the following should the benched team members do NEXT?

A.

Find a new project.

B.

Check in with a functional manager.

C.

Report to the project manager.

D.

Contact the project sponsor.

Full Access
Question # 85

The internal project sponsor is frustrated by a lack of concise, regular updates regarding the status of a

project.

Which of the following changes would BEST satisfy the project sponsor?

A.

Add the project sponsor to all project email correspondence moving forward

B.

Include the project sponsor in all project meetings moving forward

C.

Add a new line to the communications plan to provide a weekly status report with a dashboard

D.

Include the project sponsor in the daily stand-up with the entire project team

Full Access
Question # 86

A project team learns that potential remodeling on the production floor might occur during the execution phase of their project. The project team starts debating the different options available to keep delivering without adjusting the schedule. Which of the following risk activities is being performed?

A.

Mitigation

B.

Quantification

C.

Planning

D.

Identification

Full Access
Question # 87

The chairperson of the board is visiting from another country and wishes to meet the project team members. The next project team meeting will be held next week, but the chairperson is leaving before the meeting. Which of the following actions should the project manager take?

A.

Schedule a conference call for the team meeting and invite the chairperson.

B.

Arrange an impromptu team meeting with the chairperson.

C.

Email the chairperson the meeting minutes from the scheduled meeting

D.

Invite the chairperson to the next project team meeting

Full Access
Question # 88

During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.

Which of the following documents would contain these items?

A.

Business case

B.

Requirements document

C.

Project timeline

D.

Task plan

Full Access
Go to page: