A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
A senior manager asks a project manager for an estimated budget on a new project.
Which of the following is the BEST step for the project manager to take?
Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?
The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.
Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)
Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process.
Which of the following conflict resolution techniques has the project manager utilized?
A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?
A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?