Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (PMBOK 7th Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 217

A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?

A.

Work to understand the key stakeholder's concerns and provide feedback in regular project status reports

B.

Arrange an ad hoc meeting to address the key stakeholder's concerns with team members

C.

Reinforce with the key stakeholder that the project is performing on schedule\

D.

Escalate the situation to the project sponsor because the key stakeholder's behavior is impacting progress

Full Access
Question # 218

A software delivery project is in the execution phase. The project team has identified a need for an additional server as the software requires more data storage space than planned for. Without the additional server, the project delivery cannot continue.

What should the project manager do?

A.

Use the project budget and procure a new server before raising a change request.

B.

Request that the requirement is funded with the business operational expenses.

C.

Apply contingency reserves to procure a server that fits the requirement.

D.

Raise a change request and obtain approval from the project owner.

Full Access
Question # 219

A project manager is working on a software development project. Software development will be carried out through a partnership with a vendor based on a list of initial requirements not yet completely defined.

What type of contract and project approach should the project manager consider?

A.

Time and materials (T&M) with an agile approach

B.

Cost reimbursable contract with a predictive approach

C.

Fixed-price contract with a predictive approach

D.

Memorandum of understanding (MOU) with an agile approach

Full Access
Question # 220

A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not submit the reports. Their excuse is that these activities are consuming too much time.

How should the project manager handle this situation?

A.

Remind the contractor to join the meetings and submit their report as this is their commitment.

B.

File a claim for not fulfilling the contract terms in accordance with alternative dispute resolution.

C.

Compromise with the contractor to only attend the weekly meetings without submitting the reports.

D.

Assess the situation as a risk and reach out to the contractor to check the origin of this resistance.

Full Access
Question # 221

A project team has obtained additional team members from different time zones. As a result, there are full-day delays in the work being completed because there are questions from team members from opposite time zones.

What should the project lead do?

A.

Meet each team member during their work hours to ensure all questions are answered in a timely manner.

B.

Inform all team members that they are required to check for messages every few hours to ensure fast response times.

C.

During daily check-ins, compile questions, coordinate with all team members, and agree to meet.

D.

Escalate to the project sponsor and request to replace certain team members so the time zones are aligned.

Full Access
Question # 222

During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.

What should the project manager do next?

A.

Divide the team into small groups to avoid future arguments and delays.

B.

Ask the human resources (HR) department to replace the team members.

C.

Make a decision based upon the project manager's knowledge and expertise.

D.

Meet with the team members to discuss the priority of the project schedule.

Full Access
Question # 223

A project manager received several complaints from different project team members related to an unnecessary additional step the functional lead implemented as a preference. The project team members' work has been affected by this and they have missed a few deadlines.

What should the project manager do to address this concern?

A.

Recommend the functional lead meet with the project team members to convince them to accept the change.

B.

Document the additional step from the functional lead and adjust the timelines to accommodate the change.

C.

Ask the functional lead to remove this additional step as it is not vital to the project.

D.

Advise the team that the functional lead's preference should be taken into consideration.

Full Access
Question # 224

A project manager is leading the development and delivery of a strategic product that must be delivered on time. The project is facing technical issues that could significantly impact the budget and ability to deliver some of the product features.

What should the project manager do first to resolve the issue?

A.

Record the situation in the risk register and communicate it to stakeholders.

B.

Assess the impact of the feature on the project and ask for a contingency.

C.

Schedule a meeting with the team and management to discuss options.

D.

Develop a quality management plan to clearly identify how features should be classified.

Full Access
Go to page: