Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2024 Version)

Go to page:
Question # 217

The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?

A.

Issue log

B.

Project management plan

C.

Risk management plan

D.

Risk register

Full Access
Question # 218

During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.

What should the project manager do next?

A.

Discuss approval of the change request in the next project meeting

B.

Perform a risk assessment on the required change request.

C.

Evaluate the change request against the project scope statement

D.

Ask the sponsor for more funds to cover the change request

Full Access
Question # 219

During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule What should the project manager do first?

A.

Update the issue log and act to minimize the impact

B.

Update the schedule to include the delay

C.

Add the risk and the delay to the risk register

D.

Escalate to the management team for delay approval

Full Access
Question # 220

A company wants to increase the commercial value of one of its products in a highly competitive market In order to do this, the company commissions a project to create a prototype The team constructs the prototype incrementally Which action should the project manager take as a priority?

A.

Emphasize the use of Kanban methodology.

B.

Ensure the project sponsor is aware of the go-to market date

C.

Deliver business value as soon as possible

D.

Implement a plan-do-check-act (PDCA) cycle

Full Access
Question # 221

The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right

Full Access
Question # 222

During the design phase of a project the project manager notices that the schedule performance index (SPI) is 1 8 and the cost performance index (CPI) is 0 1 In a weekly meeting with top management, the project manager reports concerns about these indicators However the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project

What should the project manager do?

A.

Monitor the project sponsor but understand that it is normal to spend more money in the design phase of a project.

B.

Stop crashing the schedule

C.

Manage the project sponsor closely and revise the project's resource management plan to improve indicators

D.

Use a resource-levelling technique

Full Access
Question # 223

In a software development project, the product owner and development team agree on a sprint backlog The highest priority in the backlog is to build a payment module The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.

What should the project manager do?

A.

Let the developers focus on the refactoring work and discuss it in the retrospective

B.

Restate to the developers the importance of focusing and meeting the sprint goal.

C.

Praise the developers for their proactivity and focus on quality.

D.

Escalate the issue to the developers’ functional managers

Full Access
Question # 224

During the course of a project the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings

How should the project manager handle this?

A.

Communicate directly with the director and inform them of the communications management plan

B.

Communicate directly with the client stating that any scope changes must go through the project manager

C.

Review the stakeholder engagement plan and put in place any existing actions

accordingly

D.

Discuss the issues with the project team and let them know that the project manager will handle scope changes

Full Access
Go to page: