Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2024 Version)

Go to page:
Question # 241

From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?

A.

Inform the client that extra resources will be added to give the client more time for reviews.

B.

Update the project risk register with the potential for delays

C.

• Work with the client on an acceptable amount of time for document approval

D.

Inform the client of their responsibility in relation to document approval

Full Access
Question # 242

A company is working on a project and is using a hybrid approach to streamline a customer service process. At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.

What should the project manager do to support the business analyst?

A.

Assign resources to coach the business analyst

B.

Ask the business analyst to focus on their work allocation for the needs of the project

C.

Create reports to inform the business analyst about the schedule and project cost

D.

Provide the business analyst with access to the financial and scheduling information

Full Access
Question # 243

During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?

A.

The updated benefits management plan

B.

The updated scope management plan

C.

The updated project management plan

D.

The updated communications management plan

Full Access
Question # 244

A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned The SME asks the project manager to write, document and include it in the lessons learned register

What should the project manager do?

A.

Assign the documenting task to a project team member

B.

Ask the SME to document and capture the occurrence.

C.

Request the SME to wait until the project closure phase.

D.

Take ownership of documenting this information

Full Access
Question # 245

A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing

What should the project manager review?

A.

The project charter and scope statement

B.

The requirements traceability matrix

C.

The business requirement documents (BRD)

D.

The WBS dictionary

Full Access
Question # 246

A project manager accepts a delivery at the project site but the items are of a poor quality The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected

What should the project manager do going forward?

A.

Allocate extra time to inspect deliveries for quality assurance upon arrival at the site

B.

Review the contract requirements and ask for the applicable evidence for quality assurance

C.

Have the vendor issue the quality documentation prior to the next delivery.

D.

Call the vendor and have them verbally guarantee the quality of the next site delivery

Full Access
Question # 247

A project for Company A was successfully delivered within scope schedule, and budget by the end of the last iteration However during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.

What should the project manager have done to avoid this perception?

A.

Involved the business stakeholders in the sprint review

B.

Defined product backlog priorities with the sponsor and key stakeholders to deliver business benefits

C.

Implemented a closing survey for key stakeholders

D.

Confirmed that there is a communications management plan in place to make business stakeholders aware of the success

Full Access
Question # 248

A high-performing team member’s performance has been consistently increasing over the past year, leaving other peers behind The project manager has been reluctant to publicly recognize the team member’s contributions for fear of discouraging others The project manager is also concerned that the team member may leave if not rewarded for the contributions made.

What should the project manager do?

A.

Promote the higher performing team member to a higher position

B.

Request the high-performing team member to mentor the other team members

C.

Remind the high-performing team member to focus on shared rewards rather than individual rewards

D.

Reward the high-performing team member privately to avoid team disruption

Full Access
Go to page: