11.11 Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 441

A project manager is newly appointed to an ongoing project that will develop a new solution using an affiliate of the company. The deploying

resources will come from another entity of the company. When asked to confirm the availability of the deploying team, the deploying manager declined.

What should the project manager do first?

A.

Reschedule the project taking this new information into account.

B.

Refer to the project's resource management plan.

C.

Ask the project sponsor for external resources.

D.

Create a change request to be validated by the project sponsor.

Full Access
Question # 442

An international client contacted a software development company to build out a

software product, and an agile project manager was assigned. At one of the review meetings,

the client complains that a feature mentioned at the initial debriefing was not implemented.

What should the project manager do?

A.

Include the mentioned feature in the prioritized requirements list.

B.

Assign a team member to immediately start working on that feature.

C.

Review the original project documentation to confirm.

D.

Treat it as a change request and assess the effect on the project's goals.

Full Access
Question # 443

An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.

Which two project events will assist the project manager to ascertain if this is the case? (Choose two)

A.

Requirements analysis

B.

Retrospective

C.

Sprint planning

D.

Standup

E.

Backlog refinement

Full Access
Question # 444

A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority. What should the new project manager do next?

A.

Refer to the project charter

B.

Review the project resource matrix

C.

Assess the stakeholder register

D.

Update the communications management plan

Full Access
Question # 445

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

A.

The project should have constructed training centers in the remote towns.

B.

The project did not identify and engage the correct stakeholders.

C.

The project should have representatives in all the remote towns.

D.

The project did not fully engage the project sponsor.

Full Access
Question # 446

An agile leader is working on a complex project that is entering the final phase where solutions from different vendors are being integrated. This is the most critical delivery stage for the project

How should the agile leader ensure successful delivery?

A.

Ensure participation from all team members

B.

Ask the client to attend all daily calls.

C.

Ensure cross-departmental teams are colocated

D.

Request additional project resources

Full Access
Question # 447

A project is about to close and the project manager is p Set up a meeting to perform a root cause analy reparing a draft of the project closure report. The project sponsor has approached the project manager to stay on longer to ensure the benefits in the charter are tracked as completed However, some of the benefits will not be realized until 1year after project implementation.

What should the project manager do?

A.

Explain to the project sponsor that the project manager is only accountable for managing the project scope budget quality and schedule

B.

Document who will be tracking benefits realization what will be tracked and when it will be tracked in the project closure report

C.

Explain to the project sponsor that they are accountable for tracking benefits realization after project completion

D.

Discuss extending the project manager's allocation to the project until all benefits are realized with the project management office (PMO)

Full Access
Question # 448

A project requires testing of the final product to be done at another department's

testing facility, which is known for having low availability. This situation could potentially

impact the project schedule.

What should the project manager do next?

A.

Update the risk register.

B.

Update the issue log.

C.

Update the lessons learned register.

D.

Update the project schedule.

Full Access
Go to page: