Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps
A project that is using an incremental approach has colocated team members and is using a kanban board to visualize the work in progress
(WIP). A key external stakeholder requests that all project activities be placed on hold until a status report is distributed.
What should the project manager have done to avoid this situation?
A project manager in a matrix organization has been assigned to a system solution project with tight time lines. There are two resources assigned as part of the solution
team: one who is experienced and one who is new. During development, the project manager notices that the resources disagree on the solution approach.
What should the project manager do next to deliver a reliable solution?
A project manager is assigned to a new project. The project is for a new product that the company wants to launch as soon as possible to test market readiness. The project is part of a large business transformation, and the objective is to open delivery channels for the new product.
Which delivery approach should the project manager recommend?
Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A's front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release.
What should the project manager do to obtain agreement from both companies and acceptance from marketing?
A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team
member's deliverables do not meet the requirements.
What should the project manager do first?
A project manager is looking for ways to keep the budget on track throughout the project life cycle.
What should the project manager do to ensure that happens?
The change control board (CCB) has approved a change request to add a new component within a product. The operations manager discovers the change after its approval and complains that the implementation of the change will cause significant disruption to the production line.
What should the project manager do first?
In a global project, the main definitions were developed in country A, and the delivery of the project will be completed in phases in countries B, C, and D. Country B discovers that one of the legal requirements was not addressed.
What should the project manager have done to avoid this situation?