Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (PMBOK 7th Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 385

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

A.

Retrieve the documentation that shows the resource allocation.

B.

Examine ways of modifying the scope of the project.

C.

Adopt a resource leveling procedure to level the resources.

D.

Perform an impact analysis to see the effect on the project.

Full Access
Question # 386

A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce

the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December

might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.

What should the project manager do about this risk?

A.

Update the risk register and take advantage of the opportunity.

B.

Review the supplier's contract to understand the terms of sale.

C.

Accept the risk and update the risk register.

D.

Insist that the supplier deliver the goods on the agreed date.

Full Access
Question # 387

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.

What should the project manager do?

A.

Update the project management plan and adjust the project budget with this change request.

B.

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.

C.

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.

D.

Request a meeting with the stakeholders and their team members to inform them about this change.

Full Access
Question # 388

A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment

What should the project manager do?

A.

invite the investor to a sprint retrospective meeting to discuss the improvements of the concept and expected performance of the equipment with the team

B.

invite the protect sponsor to the sprint review meeting and nave a QSA session about the concept and expected performance of the equipment

C.

invite the product owner and the team to a discussion about the concept and expected performance of the equipment

D.

invite the investor to the design review meeting to present the concept and expected performance of the equipment and include a QSA session m the meeting

Full Access
Question # 389

A project team member wants to select specific challenging tasks in the subsequent iteration. How can the project lead help the team member in the next iteration?

A.

Assign the challenging tasks to the team member.

B.

Ask the product owner to assign the challenging tasks.

C.

Reprioritize the challenging tasks to future sprints.

D.

Coach the team member to pick up the challenging tasks.

Full Access
Question # 390

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?

A.

Adopt the same timeframe as the closed project for the current project.

B.

inform the sponsor that the activity list is not adequate for creating a schedule baseline.

C.

Create a draft schedule based on the activity list and the historical data from the closed project.

D.

Evaluate each activity duration and build a new project schedule.

Full Access
Question # 391

A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.

What should the project manager have done to avoid this situation?

A.

Ensured reports with significant information were not included in the communications management plan

B.

Defined the appropriate recipients for the report in the communications management plan

C.

Included noncompliance punishment measures in the communications management plan

D.

Validated the information and the appropriate recipients per the communications management plan

Full Access
Question # 392

Two days before the end of a sprint, a team member updates the team lead that they will not be able to complete their tasks for the sprint due to a technical difficulty. What should the agile team lead do?

A.

Inform the product owner of the issue and request that they reprioritize the delayed task.

B.

Suggest the team member get more technical training in the next quarter.

C.

Update the risk register to reflect the possible risk of a schedule delay.

D.

Raise this issue during the daily meeting to determine a possible solution with the team.

Full Access
Go to page: