Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps
A company is going through structural changes. A couple of people will leave the company as their positions were made redundant. The team members are unhappy as they do not understand why the changes are being made when the project is on track.
What should the project manager do?
The team lead on a project has left the organization and management wants to promote engineer A to this position. The project manager is confident that selecting engineer A will add problems to the project and believes that engineer B would better fit this role. The project manager discussed all of the arguments with management but their decision remains unchanged.
What should the project manager do?
During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?
During the execution of a financial project, a project manager met with the project team weekly to evaluate the project's progress. However, the sponsor requests that project performance be checked daily. The key team members disagree with this requirement and argue that they do not have enough time to go to daily meetings because they are at an executive level.
What should the project manager do first?
A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the
system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the
year. The project team is concerned that one of those tickets could be the winner.
What should the project manager do first?
A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule.
What should the project manager do?
A government procurement team has been running a vendor selection process for more than 1 year, going beyond the originally planned 6 months due to a variety of factors. Two vendors have submitted proposals that were evaluated. The project manager asked for an estimated completion date 4 weeks ago, but it was not provided.
What should the project manager do?
A project manager is appointed for the deployment of a new solution The solution will be integrated into the environment by a third-party vendor This vendor just announced a delay in delivering a key component, which will impact the project schedule.
What should the project manager do?