Searching for workable clues to ace the AACE International PSP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PSP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 9

Determine the correct formula and date for the late finish for Activity 2001.

A.

LF.2001 - 1 day -> 08-28-01.

B.

LS.2002- 1 day-> 08-29-01.

C.

LS.2002 + 1 day -> 08-30-01.

D.

LS.2002 - 1 day -> 08-28-01.

Full Access
Question # 10

Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

A.

It is calculated using the original logic.

B.

It is calculated using logic reflecting out-of-sequence progress.

C.

An out-of-sequence activity cannot resume until all predecessors are finished.

D.

There is no such thing.

Full Access
Question # 11

Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

A.

06-11-02.

B.

06-04-02.

C.

06-18-02.

D.

06-05-02.

Full Access
Question # 12

Schedule Risk may affect the following:

A.

Activity resource allocation

B.

Long-duration activities

C.

The final milestones phase milestones, critical and non-critical activities

D.

Calendar shifts

Full Access
Question # 13

An earned value-based project control system can use either of which two budgets as the basis of its calculations?

A.

Labor hours or dollars.

B.

Direct or indirect cost.

C.

Earned or budgeted cost yearly.

D.

Linear feet or dollars.

Full Access
Question # 14

How could the structural steel drawing delay have been prevented?

A.

Add a time buffer at the end of structural steel activities.

B.

Allow adequate time for review and resubmittal in the baseline schedule.

C.

Release the structural steel for fabrication concurrent with review of structural steel shop drawings.

D.

Switch to post-tensioned concrete construction.

Full Access
Question # 15

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

A.

The delay must affect the critical path.

B.

The delay must be concurrent with the delay attributable to both parties.

C.

The delay must not cause monetary harm to the defendant.

D.

The delay must affect the contractor's planned construction schedule.

Full Access
Question # 16

Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?

A.

1001 and 6001

B.

1000. 1001. and 6001

C.

9001 and 6002 and 6002

D.

1000 and 6001

Full Access