Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PSP Exam Dumps - Planning & Scheduling Professional (PSP) Exam

Go to page:
Question # 25

Which of the following statements is true?

A.

In the absence of contrary contractual language network float, as opposed to project float, there is a shared commodity between the owner and contractor

B.

In the absence of a contrary contractual language total float, as opposed to free float, there is a commodity belonging to the contractor

C.

In the absence of contrary contractual language total float, as opposed to tree float, there is a commodity belonging to the owner

D.

In the absence of contrary contractual language free float, as opposed to project float, there is not a shared commodity between the owner and the contractor

Full Access
Question # 26

As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

A.

A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be dependent on activity 6001

B.

A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to activity 6002.

C.

A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag

D.

A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be dependent on activity 6002

Full Access
Question # 27

Using the normal schedule, what is the owner's total cost of the project?

A.

S13.990.600

B.

S12.990.000

C.

S13.102.900

D.

S12.953.600

Full Access
Question # 28

Determine the driving activity for Activity 10001.

A.

Activity 11001.

B.

Activity 10002.

C.

Activity 9005.

D.

There is no driving activity for Activity 10001 in the backward pass.

Full Access
Question # 29

Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?

A.

to highlight a time when there are more holidays and work therefore will be slower and there will be more absenteeism

B.

to denote a time during which work may not progress as fast as planned and cost and risk may be elevated

C.

to provide a key to co-a weather for safety meetings

D.

to show a difference in the calendar year

Full Access
Question # 30

An earned value-based project control system can use either of which two budgets as the basis of its calculations?

A.

Labor hours or dollars.

B.

Direct or indirect cost.

C.

Earned or budgeted cost yearly.

D.

Linear feet or dollars.

Full Access
Question # 31

In its simplest form, what is the main drawback of critical path method scheduling?

A.

It requires a backward pass to calculate late dates.

B.

It assumes that resources are unlimited.

C.

It doesn't account for interdependent between activities.

D.

It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.

Full Access
Question # 32

During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?

A.

Expedite Draft Product Manual by 5 days

B.

Delay Release for Manufacture by 5 days

C.

Delay Manufacture Product by 5 days

D.

Expedite Package Product by 5 days

Full Access
Go to page: