Searching for workable clues to ace the AACE International PSP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PSP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 25

Which of the following parties is NOT a stakeholder of the Spring Highway project?

A.

ALPHA

B.

GOUGE

C.

BILCO

D.

DEVCO

Full Access
Question # 26

The EBS is established by:

A.

The contractor s planning and scheduling office

B.

The government entity with the authority to approve/stop the work

C.

The entity with the authority to fund and direct the enterprise

D.

The contractors and subcontractors

Full Access
Question # 27

Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

A.

Drafting and Proofing the Manual.

B.

Packaging only.

C.

Printing the Manual.

D.

Testing, Manufacturing and Packaging.

Full Access
Question # 28

In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?

A.

Budgeted cost of work scheduled

B.

Budgeted cost of work performed

C.

Schedule performance index

D.

Actual cost of work scheduled

Full Access
Question # 29

Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

A.

42.

B.

36.

C.

40.

D.

37.

Full Access
Question # 30

In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

A.

The schedule has too much detail to reflect an accurate critical path.

B.

Different calendars are assigned to certain activities in the logical chain.

C.

The schedule is projecting an "early completion".

D.

Certain activities in the critical path have no successors.

Full Access
Question # 31

Which of these letters, symbols or words best approximates the graphical shape of a project's cumulative BCWS?

A.

/

B.

Bell curve

C.

S

D.

_

Full Access
Question # 32

Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?

A.

8 work days

B.

18 work days

C.

7 work days

D.

15 workdays

Full Access