Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PSP Exam Dumps - Planning & Scheduling Professional (PSP) Exam

Go to page:
Question # 17

Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

A.

407 days

B.

362 days

C.

255 days

D.

267 days

Full Access
Question # 18

Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

A.

36 lifts

B.

24 lifts

C.

30 lifts

D.

48 lifts

Full Access
Question # 19

Constraints control events or activities that __________________.

A.

Affect only the forward pass.

B.

Are not based on project relationships.

C.

Affect only the backward pass.

D.

May be over-ridden by activity logic.

Full Access
Question # 20

What is a key first step in developing a critical path method schedule?

A.

Drawing a bar chart of the key phrases of the work.

B.

Defining the execution plan to meet the required scope of work.

C.

Setting out the resource to be used and its limitations.

D.

Drawing the logic diagram.

Full Access
Question # 21

The activity with the most total float is:

A.

Activity I.

B.

Activity C.

C.

Activity F.

D.

Activity D.

Full Access
Question # 22

Which of these letters, symbols or words best approximates the graphical shape of a project's cumulative BCWS?

A.

/

B.

Bell curve

C.

S

D.

_

Full Access
Question # 23

Project schedules help control all of the following EXCEPT for_____________________.

A.

Quality

B.

Cost

C.

Resources

D.

Time

Full Access
Question # 24

Identify the minimum project duration.

A.

20 months.

B.

16 months.

C.

19 months.

D.

21 months.

Full Access
Go to page: