Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?
Which of these letters, symbols or words best approximates the graphical shape of a project's cumulative BCWS?
Project schedules help control all of the following EXCEPT for_____________________.