Question # 33

What portion of Activity B is on the critical path?

A.

Last half of the activity

B.

None of it

C.

First half of the activity

D.

The whole activity

Full Access
Question # 34

In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?

A.

4001, 5001, and 6001

B.

2003 and 7001

C.

4001 and 5001

D.

2004, 4001. and 5001

Full Access
Question # 35

Why does activity 1001 have two successor activities?

A.

Because the late finish of 1001 and the late start of 7001 require two successors

B.

Because the problem could not effectively work with only one successor

C.

Because there are two defined logic paths for the work

D.

Because the duration of activities 2001, 2002 and 200.f require two successors

Full Access
Question # 36

Using the normal schedule, what is the early finish date and total float of Activity 10002?

A.

24 Nov 2023. and 24 days of tree float

B.

24 Dec 2023. and 24 days of tree float

C.

17 Dec 2023. and 4 days of total float

D.

21 Dec 2023. and 4 days of total float

Full Access
Question # 37

Which of the following phases does NOT describe the commonly accepted construction life cycle?

A.

Claims and disputes phase.

B.

Installation phase.

C.

Planning and design phase.

D.

Turnover and start-up phase.

Full Access
Question # 38

In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:

A.

ahead of schedule

B.

on schedule

C.

complete

D.

behind schedule

Full Access
Question # 39

Determine the correct formula and date for the late start for Activity 9001.

A.

The early finish is required in order to determine the answer.

B.

LS.6001 Dur.6001 -> 11-20-02.

C.

There is insufficient data provided to calculate the answer.

D.

LF.9001 Dur.9001 -> 11-20-02.

Full Access
Question # 40

Which of the following is NOT input data to the construction planning process?

A.

Input from the owner

B.

The contract

C.

Bonding capacity of subcontractors

D.

Input from the contractor