Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PSP Exam Dumps - Planning & Scheduling Professional (PSP) Exam

Go to page:
Question # 41

What is the cycle time?

A.

5 minutes

B.

17 minutes

C.

14 minutes

D.

6 minutes

Full Access
Question # 42

How many workdays occur from the start of the Product Testing to the Product Available milestone?

A.

70

B.

100

C.

60

D.

90

Full Access
Question # 43

If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

A.

The Eichleay formula

B.

Historical production rates

C.

Time impact analysis

D.

Black-Scholes model

Full Access
Question # 44

At the end of month one, did the delay to the parking structure foundation delay the project?

A.

NO.

B.

Yes, by 4 calendar days.

C.

Yes, by 14 calendar days.

D.

Yes, by 9 calendar days.

Full Access
Question # 45

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

A.

15 days.

B.

0 days.

C.

5 days.

D.

10 days.

Full Access
Question # 46

If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

A.

8 days

B.

6 days

C.

4 days

D.

5 days

Full Access
Question # 47

Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

A.

Consideration of all stakeholders.

B.

Value engineering.

C.

Project variables.

D.

Interest rate of owner's construction bonds.

Full Access
Question # 48

For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

A.

LS.11001 + 25 days.

B.

02-19-04.

C.

EF.11001.

D.

EF.11001 + 1 day.

Full Access
Go to page: