Question # 33

Which of the following cost estimating techniques uses previous, similar projects as a basis of estimating costs for the current project?

A.

Top-down estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Analogous estimating

Full Access
Question # 34

The project charter is an output of which of the following project phases?

A.

Initiation

B.

Planning

C.

Execution

D.

Closing

Full Access
Question # 35

A project manager has just completed the planning of a project, but cannot start the project execution until granted permission from the project sponsor. This is an example of which of the following actions?

A.

Stakeholder analysis

B.

Risk assessment

C.

Audit review

D.

Phase gate

Full Access
Question # 36

Which of the following conclusions can be drawn when a project has a CPI of 1.2?

A.

The project is taking longer than the estimated schedule.

B.

The project is costing less than the estimated budget.

C.

The project is taking less time than the estimated schedule.

D.

The project is costing more than the estimated budget.

Full Access
Question # 37

A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a certain time each week. One team member consistently submits late status reports. Which of the following should the project manager consider FIRST?

A.

Time zones for various work locations

B.

Necessity of weekly status reports

C.

Format of the status report

D.

Past performance reviews of the team member

Full Access
Question # 38

In order to complete the pre-project setup, which of the following is the MOST important task of the project sponsor?

A.

Obtain funding for the project.

B.

Provide quality review of the deliverables.

C.

Provide leadership to the project team.

D.

Obtain resolution of the application development issues.

Full Access
Question # 39

The change control board has requested that a project manager evaluate the impact of a major change request that will affect the timetable of several work-packages. Which of the following actions should the project manager undertake FIRST?

A.

Create a modified version of the project schedule applying the critical path method.

B.

Call a project team meeting to use combined expert judgment to accept or reject the change request.

C.

Create a Pareto chart for the outputs from the specific work-packages identified by the change control board.

D.

Crash the schedule to meet the original deadlines.

Full Access
Question # 40

Which of the following documents would a project manager review to determine all the identified risks on a project?

A.

Risk matrix

B.

Risk register

C.

Risk response

D.

Risk baseline