Which of the following cost estimating techniques uses previous, similar projects as a basis of estimating costs for the current project?
The project charter is an output of which of the following project phases?
A project manager has just completed the planning of a project, but cannot start the project execution until granted permission from the project sponsor. This is an example of which of the following actions?
Which of the following conclusions can be drawn when a project has a CPI of 1.2?
A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a certain time each week. One team member consistently submits late status reports. Which of the following should the project manager consider FIRST?
In order to complete the pre-project setup, which of the following is the MOST important task of the project sponsor?
The change control board has requested that a project manager evaluate the impact of a major change request that will affect the timetable of several work-packages. Which of the following actions should the project manager undertake FIRST?
Which of the following documents would a project manager review to determine all the identified risks on a project?