Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2024 Version)

Go to page:
Question # 497

A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?

A.

Keep the performance management as is and focus on the achievement of scope, cost, and schedule indicators.

B.

Propose an approach based on value measurement, such as the use of objectives and key results.

C.

Maintain focus on cost indicators, but remove scope and schedule as they are flexible with an agile approach.

D.

Maintain the focus on schedule indicators, but remove scope and costs as they are flexible with an agile approach.

Full Access
Question # 498

While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because

of that, each feature is taking longer than initially estimated.

What should the project manager do to address the issue?

A.

Escalate the issue to the project sponsor.

B.

Address the issue during the next sprint planning meeting.

C.

Initiate a change request to extend the project end date.

D.

Extend the dates for future project milestones.

Full Access
Question # 499

A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce

the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December

might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.

What should the project manager do about this risk?

A.

Update the risk register and take advantage of the opportunity.

B.

Review the supplier's contract to understand the terms of sale.

C.

Accept the risk and update the risk register.

D.

Insist that the supplier deliver the goods on the agreed date.

Full Access
Question # 500

During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.

A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?

A.

Allow the agile team to decide what they are able to deliver in each iteration

B.

Ask the team for additional feedback and add tasks to the task board,

C.

Hold a brainstorming session to identify the root cause of the complaints.

D.

Document the customer's complaints and critical issues in the issue log.

Full Access
Question # 501

A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a

dependency missing between:

+ Test the product

+ Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

A.

Finish to start

B.

Start to start

C.

Start to finish

Full Access
Question # 502

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component

managed by an external vendor. How should the project manager address the team member's concern?

A.

Ask the team member to resolve the issue independently to minimize further delays.

B.

Ask the team member to provide details to address the issue with the vendor.

C.

Implement fast tracking to reduce the impact of the delay on the sprint.

D.

Update the communications management plan to prevent future reoccurrence.

Full Access
Question # 503

A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion.

What should the project manager do?

A.

Assume the role of the product owner while the product owner gets familiar with the product.

B.

Schedule time to share insights with the new product owner about the product and project information.

C.

Work with the project management office (PMO) manager to generate an onboarding plan for the new product owner.

D.

Organize a team-building activity and ask the team to respect the opinions of the new product owner.

Full Access
Question # 504

A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team

to collaborate effectively.

Which three actions should the project manager take to accomplish this goal? (Choose three)

A.

Require the team to have daily mandatory meetings with the project management office (PMO).

B.

Recommend the use of formal written documentation in all project communications.

C.

Review the communications strategy with the team regularly with a view for continuous improvement.

D.

Send out a survey to review the preferred method, time frequency for communications.

E.

Compile a communications management plan with input from all stakeholders and distribute for review and approval.

Full Access
Go to page: