Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2024 Version)

Go to page:
Question # 65

A key stakeholder is refusing to participate in a crucial project stage and disagrees with the project team's approach. This situation is affecting the project team's morale.

What should the project manager do?

A.

Ask the project team to meet and document why the stakeholder's approach is incorrect.

B.

Schedule a meeting with the project team and the key stakeholder as soon as possible to discuss and agree on an approach.

C.

Discuss the issue with the project team during a project status meeting and request that they change the approach.

D.

Ask the project sponsor to meet with the project team and key stakeholder to discuss the approach.

Full Access
Question # 66

In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?

A.

Reach an agreement with the team on how to handle the situation.

B.

Reach out to the procurement team to hire a substitute for the team member.

C.

Allow senior management to decide how to proceed with the project.

D.

Convince the team member not to leave until the project is completed.

Full Access
Question # 67

Some of the more experienced members of a project team have complained about the project manager. The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

A.

Set up a team building event to bring synergy back to the project team.

B.

Adjust the project manager's management style to better fit senior team members.

C.

Ask for advice on how to be a better mentor to these team members.

D.

Meet daily with each senior team member to monitor project status.

Full Access
Question # 68

A project team created user stories after understanding the customer requirements. As the project progresses, the project manager observes that

there are too many change requests. The team feels that the outcomes they are working on are not aligned with the customer requirements.

What should the project manager do?

A.

Refer to the configuration management knowledge base for similar projects delivered in the past.

B.

Arrange for a workshop with the customer to understand the business values expected from the outcomes.

C.

Include a representative from the customer to work collaboratively with the team.

D.

Acknowledge that the current team needs improvement and hire more qualified team members.

Full Access
Question # 69

A team has had issues with behavior on an ongoing project, which is causing conflicts. As a result, the team is losing momentum and falling

behind in its sprints.

How should the project manager handle this situation?

A.

Engage a counselor to reconcile the situation between the team members affected.

B.

Control backlog assignments and reduce direct communications between team members.

C.

Revisit the ground rules and team communication protocols, and discuss what is happening.

D.

Require team members experiencing the conflicts to take a day off from work.

Full Access
Question # 70

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion.

What should the project manager do?

A.

Assess the schedule impact and evaluate the most feasible solution to keep the project on track.

B.

Ship the package as is, complete carryover work on-site, and back charge the vendor for the rework.

C.

Initiate regular conference calls with the vendor for status updates to keep this item in focus.

D.

Hold the shipment until the rework is completed at the vendor's facility to eliminate extra work on-site.

Full Access
Question # 71

A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have

recently been requested.

What should the project manager do next?

A.

Reject the changes and stay the original course as initially agreed with the client.

B.

Review the changes and make the decision based on the project team's recommendations.

C.

Discuss the changes with the client and jointly make the decision on how to proceed.

D.

Review the risk register to see if mitigations have already been outlined for this scenario.

Full Access
Question # 72

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?

A.

Ask the project team to review and modify all of these reports.

B.

Ask the sponsor to meet with the stakeholder to diffuse the situation with the reports.

C.

Explain to the stakeholder that these are the approved templates for the reports.

D.

Ensure that the reports comply with the communications management plan.

Full Access
Go to page: