Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2024 Version)

Go to page:
Question # 97

A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this project?

A.

Add time reserve in the project schedule to allow extra time for the stakeholders to make decisions.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholders ahead of time.

C.

Work with the available stakeholders to make business decisions and keep all unavailable stakeholders informed.

D.

Schedule meetings with all of the stakeholders to make business decisions when needed.

Full Access
Question # 98

During daily team standup meetings, team members constantly ask about which tasks they should focus on first. How should the project

manager ensure the team is fully productive?

A.

Review the project backlog during the team's standup meeting.

B.

Encourage project team members to prioritize the product backlog.

C.

Ensure team members are working according to the project plan.

D.

Work with the product owner to ensure the project backlog is prioritized.

Full Access
Question # 99

In an effort to modernize the technology for a project, the project manager has been discussing risk prioritization with the project team. The project manager determines that additional parameters are needed to iteratively assess and prioritize the project risks.

Match the project manager's goals on the left with the relevant risk parameter on the right.

Full Access
Question # 100

A project manager is leading a technically complex project. The project is part of a strategic program of work and the first to use an agile approach. One of the board members is interested in attending a meeting to see how the delivery of the project scope is progressing.

What should the project lead do?

A.

Invite the board member to the next daily standup.

B.

Invite the board member to the next sprint retrospective.

C.

Invite the board member to a separate demo.

D.

Invite the board member to the next sprint review.

Full Access
Question # 101

A project manager is part of a balanced matrix project organization. The project manager will receive all work performance updates directly from the new sourcing

department head who has no time to spare to give the project manager the information.

What should the project manager do?

A.

Request information directly from the sourcing department team members.

B.

Present the situation to the manager of the sourcing department head.

C.

Discuss the situation with the company project sponsor for advice.

D.

Work out a resolution in consultation with the sourcing department head.

Full Access
Question # 102

A project manager is leading a strategic and competitive advantage project for a healthcare organization that is in its testing phase. The team has

been working on this project for 6 months, and the morale of the team is low due to the schedule.

What can the project manager do to motivate the team?

A.

Continue to perform the last phase of the project with the project team as this will benefit the organization and provide a competitive edge.

B.

Talk to the business team about the project phase and the team's commitment, and request a monetary reward for the team.

C.

Speak with the project management office (PMO) and request a 2-week extension of the schedule so the team can have rotational time off.

D.

Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project.

Full Access
Question # 103

A project manager has been assigned to lead a software project to generate savings at an important financial institution. Initially, the duration of the project was 13 months,

but due to various issues during execution, the project was extended to 16 months. By month 11, the expected savings were exceeded but not all of the functionalities

planned for that date were fulfilled.

How should the project manager inform the stakeholders of the project's progress?

A.

Report that the project has not fulfilled all the expected functionalities.

B.

Complete the outstanding functionalities before informing the sponsor of the project progress.

C.

Communicate the benefit expectations and the action plan for the pending functionalities.

D.

Send an email with the monthly project progress to all relevant stakeholders.

Full Access
Question # 104

A self-organizing team for a critical project is consistently delivering value according to their commitments. During a retrospective, the project manager observed that most of

the team members were stressed due to over commitments.

What should the project manager do?

A.

Help the team members by organizing regular stress-relieving and team- building sessions.

B.

Request additional resources to continue delivering value while reducing team stress.

C.

Support the team during the planning phase to only commit to what they are able to deliver.

D.

Ask individual team members to plan staggered leave to avoid becoming stressed.

Full Access
Go to page: