Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2025 Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 129

A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.

What should the project manager do?

A.

Assign a development team member to have the responsibility of managing dependencies.

B.

Suggest that each project develops a high-level plan to monitor the dependencies

C.

Recommend switching to a predictive approach to have detailed plans to manage the dependencies

D.

Continue the project with 2-week iterations as dependencies will be managed individually

Full Access
Question # 130

A supplier was supposed to mobilize a government-issued, licensed piece of

equipment two days ago, but did not. The procurement manager was informed that the

supplier failed to check the validity of the license, which expired last week. The supplier had

already submitted an application to the authorities, but it generally takes one to three weeks to process the application, which will affect the critical path.

Which action should the project manager take?

A.

Update the project team on the delay so that resources can be utilized elsewhere.

B.

Analyze the schedule and look for fast tracking and crashing alternatives.

C.

Review the terms of the contract in order to determine next steps.

D.

Update the lessons learned register to serve as an input for future material transactions.

Full Access
Question # 131

A junior team member escalates an issue to the project manager about another

member's interpersonal skills causing the team to be less effective.

What should the project manager do first?

A.

Have the team members resolve the issue on their own.

B.

Highlight the impact of their behavior and motivate the team member to make improvements.

C.

Gather information and find the root cause of the problem.

D.

Document the escalated issue and address it at the end of the project.

Full Access
Question # 132

A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.

Full Access
Question # 133

A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.

How should the project manager approach this situation?

A.

Understand the customer's perspective and provide mentoring on agile mindsets.

B.

Call for an internal team retrospective and create an improvement action plan.

C.

Ask the customer to work with the product owner to prioritize all requests.

D.

Work with the team to receive customer directions and improve the process.

Full Access
Question # 134

A year after implementing a policy change to improve diversity and inclusion within two teams, there is increasing conflict within the company What should have been done to prevent this conflict?

A.

The organization should have introduced the concept of diversity broadly

B.

The leadership team should have worked closely with the marketing team to get insight on diversity

C.

Organization-wide diversity training should have been provided to the workforce

D.

The critical departments in the organization should have been involved in this exercise

Full Access
Question # 135

A project is being initiated, and almost every resource available on the project team is a recent university graduate. What should the project manager do to ensure their engagement with the project?

A.

Provide clear direction on the work to be done and its alignment to the major objectives of the organization, using technology to communicate.

B.

Establish a clear hierarchical environment and allow them to navigate through the project faster using social networks.

C.

Foster proactive decision making and develop a hierarchy to approve decisions based on different levels of complexity.

D.

Create an environment that encourages leadership, translates ambitions into growth opportunities, and rewards overtime workers.

Full Access
Question # 136

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?

A.

Escalate the issue to the team's manager.

B.

Remove some of the team members.

C.

Review the roles and responsibilities document.

D.

Develop working agreements with the team.

Full Access
Go to page: