Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2024 Version)

Go to page:
Question # 89

A project manager is working on a large IT project. During a review for one of the deliverables, a stakeholder raised a concern about the final product.

What should the project manager do first?

A.

Set up a meeting with the product owner to discuss the stakeholder's concern.

B.

Discuss this with the team and review the project requirements documentation.

C.

Set up a meeting with the sponsor to discuss the details of the deliverable.

D.

Discuss this with the team and put the stakeholder's concern in the issue log.

Full Access
Question # 90

An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers less than committed. A new project lead with a strong technical background has been assigned to the project.

What should the project lead do?

A.

Ask that estimations be provided only by senior developers.

B.

Allocate more time for estimation in the sprint planning.

C.

Review and update the estimations in the daily standup.

D.

Recommend a different estimation method in the retrospective.

Full Access
Question # 91

A project to construct an electricity generation plant is on site near a nature reserve. An environmental activist group is questioning the need for

the project. The customer has informed the project manager to disregard the group as they are not in support of the project.

What should the project manager do next?

A.

Ask the customer to contact the activist group and let them know the project status and completion date.

B.

Add the activist group to the list of stakeholders and analyze the impact they may have on project delivery.

C.

Obey the directive from the customer since they are funding the project and are the most important stakeholder.

D.

Request the project team disregard all communication from the activist group and continue with their project work.

Full Access
Question # 92

A project manager is newly appointed to lead a project team that will be working remotely. The project manager decided to use a set of tools that

worked well for previous projects. However, a few team members are not happy with this plan.

What should the project manager have done to avoid this?

A.

Delegated the responsibility of selecting the collaboration tools to the project's technical lead.

B.

Met with the project team to determine their collaboration needs and identified tools that will work best.

C.

Allowed the project team members to use the tools that will work best for them for this project.

D.

Asked the project sponsor for approval to purchase the newest collaboration tool on the market.

Full Access
Question # 93

A project manager is managing a project to deploy new software to 200 end users. During the implementation, there is a missed process that

caused some of the users to lose their computer data.

What should the project manager do first?

A.

Meet with the team to discuss the root cause and encourage the team to take note of it and continue to focus on the deployment.

B.

Record this case until the final lessons learned session is complete to prevent impacting the team's morale during implementation.

C.

Meet with the team members and request they conduct a review of the case by providing feedback as lessons learned.

D.

Invite a consultant to review the process in order not to repeat the same issue and share the results with the team.

Full Access
Question # 94

During the lessons learned workshop, one stakeholder mentioned that the project was unsuccessful as it did not deliver the expected business value. What should the

project manager do to address this concern?

A.

Review the project management plan tasks with the stakeholders.

B.

Review the project management plan budget with the stakeholders.

C.

Review the business benefits realization plan with the stakeholders.

D.

Review the communications management plan with the stakeholders,

Full Access
Question # 95

A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the team had difficulty meeting the iteration goals.

How should the project manager handle this situation?

A.

Inform the human resource (HR) department about the issue.

B.

Allow the project team to discuss the problem with this team member.

C.

Discuss the issue with the team member's functional manager.

D.

Speak to the team member regarding the need to improve performance.

Full Access
Question # 96

A customer is concerned with the quality of the product delivery, as the production deployment is approaching. What should the project manager do next to ensure acceptance of the deliverables?

A.

Test product integration in accordance with the requirements.

B.

Evaluate the quality checklist for product compliance.

C.

Review the approved exit criteria for the product.

D.

Verify the production budget before advancing the product.

Full Access
Go to page: