Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2024 Version)

Go to page:
Question # 73

A member of the project team always extends discussion topics, taking more time than necessary during project team meetings. Other team members feel this member is not being considerate of their time.

What should the project manager do?

A.

Explain to the team that open discussions are needed but remind the team to follow the ground rules.

B.

Ask this member to only discuss the current topic to achieve team efficiency.

C.

Ask the team to accept the input from this particular member as their input may be useful.

D.

Allow the self-organized team to discuss the situation among themselves and come to a resolution.

Full Access
Question # 74

A project manager works for a company that has a reputation of delivering environmentally sustainable projects. During the half-yearly review of the project, the project manager raises serious concerns with

the project sponsor regarding the project's viability and success. There are some stakeholders who oppose this project on the grounds of compromising land erosion.

What should the project manager do?

A.

Propose to close the project because it no longer fits the business values of the organization.

B.

Calculate earned value (EV) because the project manager is forecasting a loss for this project in the yearly review.

C.

Calculate float on the project because it has severely affected the project's major critical path.

D.

Request additional resources from the business unit manager due to the project's complexity.

Full Access
Question # 75

A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second

iteration, the project manager realizes that a significant regulatory feature is missing in the project backlog.

What should the project manager do?

A.

Ask the product owner to add the missing feature in the backlog.

B.

Invite stakeholders to discuss the impact of adding the regulatory feature.

C.

Estimate the related cost and ask for a project extension.

D.

Increase the capacity of the team to include the missed feature.

Full Access
Question # 76

A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%.

During the iteration retrospective, the team realizes that the complexity of the work was underestimated.

What should the project manager do?

A.

Update the issue log and escalate it to the project sponsor.

B.

Meet with the team to review internal actions to resolve the situation.

C.

Ask the technical manager to help the team with the issue.

D.

Ask to replace some team members with more experienced ones.

Full Access
Question # 77

A project manager is leading a project that includes several organizations with unique corporate cultures. These diverse corporate cultures are affecting project expectations. The varying expectations often lead to conflicts, which often require the project manager's involvement.

What should the project manager do first to evaluate the cultural differences within the organizations?

A.

Establish a probability and impact matrix and plan response criteria.

B.

Disregard the situation since it is not hindering the project deliverables.

C.

Develop a joint policy among the various organizations.

D.

Escalate the issue to the project sponsor and seek their guidance.

Full Access
Question # 78

A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.

What should the project manager do next?

A.

Ensure the team follows standard operating procedures (SOP) for creating a stakeholder report.

B.

Instruct the team to make only a graphical representation of all the data for the report.

C.

Instruct the team to conduct a meeting with the stakeholders before finalizing the report.

D.

Instruct the team to analyze and interpret the data before including it in the report.

Full Access
Question # 79

A mid-size capital project has shared resources from the company's contract department. During the execution phase, the project team observed

a delay in contracting. After communicating with the contract department, the project manager found the contract team is prioritizing other

contracting jobs because they are not part of the project team.

What should the project manager do first in this situation?

A.

Report the issue to higher management and seek their direct involvement to complete the job from the contract department.

B.

Arrange a meeting with the contract department to build trust and commitment by recognizing their critical support to the project.

C.

Arrange several meetings with the contract department and ask them to contract the project as it is critical for project success.

D.

Communicate with the contract manager to commit a budget for the resources required for project execution.

Full Access
Question # 80

A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is dissatisfied, stating that the deliverables do not meet the quality specifications.

What should the project manager do in this situation?

A.

Notify the stakeholder that arbitration procedures will be followed.

B.

Inform the project sponsor of the stakeholder's dissatisfaction.

C.

Document the issue in the issue log and send a report to management.

D.

Review the requirements traceability matrix and conduct inspections.

Full Access
Go to page: