Special Summer Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMI-ACP Exam Dumps - PMI Agile Certified Practitioner (PMI-ACP)

Go to page:
Question # 9

A team member on a self-directed team is concerned that a feature the customer wants is outside of what the team will be able to deliver. What should the team member do next?

A.

Escalate the concern to the project sponsor for necessary action

B.

Adjust the feature to make it work as needed

C.

Work directly with the customer to arrive at a suitable compromise

D.

Log this into the risk register and inform the team at the next standup meeting

Full Access
Question # 10

A customer has difficulty explaining how the highest priority feature will work. What should the agile project manager do?

A.

Create a time-boxed spike story to reduce the technical risk of the feature.

B.

Commence an iteration 0 for the customer and the team to investigate the feature.

C.

Facilitate the decomposition of the feature epic into more manageable user stories.

D.

Facilitate a just-in-time exploration of the functionality by the customer and the team.

Full Access
Question # 11

An infrastructure team had to revamp so downstream channels could consume data from the data lake, thereby improving operational efficiency for the end customers. Which primary components should the product manager consider while plotting performance and dependencies on the product roadmap?

A.

Product vision, business objectives, themes, timeframes, and disclaimers

B.

Product improvements, resource management, risk management, and deadlines

C.

Product goals, strategic objectives, major features, and release plans

D.

Features, stages of development, technology and infrastructure, dependencies, and risks

Full Access
Question # 12

An executive sponsor of a new scrum team actively attends scrum ceremonies How does this benefit the team?

A.

It helps the team to focus on and meet sprint goals.

B.

It reminds the team about who sponsors the project.

C.

It provides high-level project updates to the sponsor

D.

It helps to quickly resolve issues using the sponsor's Influence

Full Access
Question # 13

An agile team has received several new features to be added to the product backlog. The team is struggling to provide a reasonable estimate for feature development due to a lack of experience.

How should an experienced agile practitioner assist the team?

A.

Add a task to the product backlog to allow the team time to investigate and experiment prior to estimating.

B.

Add a task to the product backlog to allow the team to apply a wideband Delphi estimation technique.

C.

Add a task to the product backlog to allow the team to apply planning poker to estimate the effort.

D.

Add a task to the product backlog to allow the team to apply a three-point estimation technique.

Full Access
Question # 14

What is a specific development practice that has been effective in implementing disciplined DevOps?

A.

Put the client first.

B.

Create a safe environment.

C.

Practice continuous delivery.

D.

Manage risk.

Full Access
Question # 15

A project team held a working session with a finance team to understand the procurement process. After the meeting, while the agile lead was facilitating the value stream mapping exercise, one of the team members asked: "When calculating the cycle time, which factors should be considered?"

How should the agile lead respond?

A.

Total time and average process time

B.

Critical path and queue lengths

C.

Delays and bottlenecks in the process

D.

End date/time and start date/time

Full Access
Question # 16

On what should an agile team work to achieve predictable flow?

A.

Small user stories

B.

Simple acceptance criteria

C.

Lean features

D.

Lean backlogs

Full Access
Go to page: