The project team is ahead of schedule and beginning lo gold-plate the feature included in the current sprint. What should the agile project manager do?
A new agile team member notices that the team's current process involves excessive documentation. What should the new team member do?
During a project meeting, a team is faced with a difficult decision. After discussion and deliberation, the project leader makes the final decision and ends the discussion. This causes a team member to withdraw from future collaboration.
How could the project leader have avoided this?
The amount of information captured in the project's defects is varying within the development team. Team members are becoming frustrated with the defect quality inconsistencies and the frequent clarification required.
What should be done to address the issue?
During the iteration planning of a newly onboarded agile team, the product owner adds a set of high priority user stories into the iteration backlog. What should the team do first to define the tasks needed to implement the user stories?
During a Kanban team's daily stand up, an agile coach observes that the team seems disinterested in the work status. While it appears that there are no issues with flow, there is a marked lack of attention to team effort. When the agile coach queries the team for reasons, members explain that work continues to be scheduled with no end in sight.
What should the agile coach do?
A product that recently went to market is receiving a great deal of attention from upper management who expresses interest by directly emailing and calling the developer team. The team expresses frustration during a standup.
What should the Scrum Master do?
A product owner asks a newly formed scrum team how many story points will be completed in a sprint. What should the scrum master do?