Question # 4

The product owner of an agile project is frustrated because the team is unable to deliver as many features as expected. The product owner asks the team to reduce test-automation levels, since the quality assurance team will test the product at project completion. The product owner expects that more features will be delivered in each iteration using this approach.

What should the agile practitioner do?

A.

Ask the opinion of key stakeholders and the client to ensure the correct approach is being used.

B.

Work with the team to use this approach and request a quality assurance iteration after every three iterations

C.

Propose to completely eliminate test automation, since this is a quality assurance function.

D.

Suggest merging the quality assurance and delivery teams to enhance each iteration's test-automation levels and reduce redundancy

Full Access
Question # 5

The executive leadership wants to understand ways to better deliver on time and on budget. What can the project team do to assist in achieving the organizational goal?

A.

Maintain and review a lessons learned repository to improve delivery of future projects.

B.

Ask each team member to post corrective action to the backlog.

C.

Engage the project management office (PMO) to take responsibility identifying lessons learned on projects.

D.

Perform a root cause analysis to identify alternative approaches for performing the next project.

Full Access
Question # 6

Based on the backlog metrics in the chart what can explain the jump in points at the end of iteration 4?

A.

The team neglected to account for support and maintenance costs associated with other supported products

B.

The team discovered that previously accepted work could be greatly improved and added story points associated with thatwork.

C.

The team realized that some stories were underestimated relative to other stories and reestimated as needed

D.

The team learned that the product owner needed to increase the output in the next release

Full Access
Question # 7

Stakeholders have conflicting requirements, and the product owner is struggling to decide which user stories to write. What should the product owner do?

A.

Ask the agile practitioner to help write the user stories.

B.

Ask the agile team to facilitate a story-writing workshop.

C.

Ask subject matter experts (SMEs) to help write the user stories.

D.

Ask the agile practitioner to facilitate a story-writing workshop.

Full Access
Question # 8

Which option describes how risk should be managed in an agile project?

A.

Since using an agile methodology minimizes risk in project management, the project team can focus on delivering business value over managing risk.

B.

Project team members would each be responsible for identifying and managing risks for the individual user stones they have been assigned

C.

All stakeholders are responsible for identifying risks during standups, retrospectives, and other team meetings.

D.

The product owner is responsible for identifying risks and entering them into the backlog so that their mitigation can be prioritized.

Full Access