Special Summer Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMI-ACP Exam Dumps - PMI Agile Certified Practitioner (PMI-ACP)

Go to page:
Question # 41

An agile team provides feedback that user stories include insufficient details to understand the requirements. What should the agile practitioner do?

A.

Coach the product owner to update only the acceptance criteria.

B.

Instruct the agile team to fix the user stories during the next retrospective.

C.

Facilitate a user story workshop with the agile team.

D.

Inform the product owner's manager that the work items provide insufficient detail.

Full Access
Question # 42

A team member does not understand what the project risks are or the impact that they could have. How should an agile leader communicate risks in a way that the team will understand?

A.

Create a RAG chart (responsible, accountable, consulted, informed) that identifies who is accountable for each risk.

B.

Create a Gantt chart that includes slack to accommodate for unknowns.

C.

Create a communications management plan that details who is responsible for communicating risks.

D.

Create a risk burndown chart showing the reduction of risks overtime.

Full Access
Question # 43

Over the last two sprints, a number of potential problems have threatened the team's ability to hit the targeted release date. What should the agile practitioner do?

A.

Deal with the issues in a retrospective if they ever come up again.

B.

Create a task board to track issues when they appear.

C.

Identify and monitor issues through a risk burndown chart.

D.

Create an issue log as an information radiator and monitor.

Full Access
Question # 44

During a project's last iteration, an agile team struggled with a feature's delivery due to the lack of a required skill. The project has already incurred a five-day delay. A further delay of at least 10 days is anticipated.

What should the agile project leader have done to avoid this situation?

A.

Provided just-in-time training of the required skill to specific team members

B.

Lowered the feature's priority until a team member acquired the skill to build it

C.

Assigned the feature to another agile team that had members with the required skills

D.

Ensured that the team was comprised of cross-functional, generalized specialists

Full Access
Question # 45

When working on a new product, what should an agile team do to ensure alignment with external stakeholders?

A.

Hold a kick-off meeting to assign roles.

B.

Review the project vision statement.

C.

Ask the product owner for a detailed product-specification document.

D.

Work with the scrum master to ensure that agile principles are followed.

Full Access
Question # 46

A product owner is responsible for a new product. The internal customer questions using an agile approach because they need a product that works without any bugs or missing features once it is launched.

What should the product owner do?

A.

Plan regular retrospectives with the development team to continuously improve processes to eliminate any potential issues with the product.

B.

Apply an agile approach to write the specifications in an incremental way and develop the product once the final specifications are agreed upon.

C.

Set up test-driven development to focus on customer requirements and eliminate issues in the software as testing progresses,

D.

Ask the customer to provide additional representatives to help test and evaluate the product for early and frequent feedback.

Full Access
Question # 47

The team is considering committing to 44 story points for the upcoming sprint. Based on the

velocity chart, what advice should the scrum master offer the team?

A.

Reduce the commitment to 40 story points to ensure a higher chance of meeting the commitment.

B.

Maintain a commitment of 46 story points, representing the most frequently completed velocity.

C.

Increase the commitment to 48 story points to push the team toward higher performance.

D.

Commit to 44 story points as it aligns with the team's average velocity for completed story points.

Full Access
Question # 48

A product owner adds user stories to the backlog on a daily basis. The stories are vague requests, and the product owner expects the details to be clarified once the team works on the prioritization list.

How should the team members address this challenge so that the prioritization meeting does not become a brainstorming session?

A.

Ask the product owners to invite a subject matter expert (SME) to the meeting so the prioritization meeting will be more effective.

B.

Ask the product owner to review their items with the product owner's teammates before adding user stories to the backlog.

C.

Ask the product owner to schedule a meeting with a subject matter expert (SME) to review items before adding user stories to the backlog.

D.

Ask the product owner to review the stories with the scrum master before the prioritization meeting takes place.

Full Access
Go to page: