Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-200 Exam Dumps - PMI Agile Certified Practitioner (PMI-ACP)®

Go to page:
Question # 9

A full cycle of design-code-verifyrelease practiced by extreme Programming (XP) teams is called:

A.

Story

B.

Timebox

C.

Iteration

D.

Burndown

Full Access
Question # 10

How is the participatory design process characterized?

A.

A well-planned and well-documented process is documented for each of the iterations in the project.

B.

Users including project team members participate in the planning process for the project plan.

C.

End users participate and assist in the design process from the beginning of the project.

D.

A high level brainstorming process is conducted for the project team and the project sponsor.

Full Access
Question # 11

In Agile projects, how are planning outputs shared with stakeholders?

A.

Using the most highly visible method possible

B.

On a need-to-know basis depending on role

C.

According to the project communications plan

D.

Through a series of stakeholder meetings

Full Access
Question # 12

Applying the Pareto rule when prioritizing the Product Backlog means that:

A.

features that are lower priority are more likely to slip to the next iteration.

B.

the value of a feature is not realized until the feature is complete.

C.

more recent requests are usually more important to the business.

D.

a small percentage of the work will provide a large percentage of the value.

Full Access
Question # 13

What is the first thing that a team should do to estimate user stories for a project?

A.

Sort the user stories according to priority.

B.

Schedule a team meeting to understand them.

C.

Define the story points measure.

D.

Estimate through function point analysis.

Full Access
Question # 14

When interacting with team members, the Agile project manager should:

A.

Ask team members to do things by phrasing the statement as a request rather than as a demand.

B.

Ignore team member input and emotions when important decisions have to be made.

C.

Proceed cautiously when requesting team members to do something likely to make them unhappy.

D.

Disagree with the team based on the merit of the issue without considering how the team is feeling.

Full Access
Question # 15

Which of the following would be most likely to assist when a customer has difficulty prioritizing stories?

A.

Split the stories into smaller ones to allow the customer to choose the pieces that they want.

B.

Have the team provide guidance into where their priorities lie to the customer.

C.

Provide additional technical details to give the customer insight into technical challenges.

D.

Have the team rewrite the stories with additional details to clarify requirements.

Full Access
Question # 16

After three iterations, the problems impeding an Agile team appear to be similar in nature to problems faced in earlier iterations. Inspection of the retrospectives for past iterations reveals information organized into columns entitled “What worked for us” and “What did not work for us. ” Based on this information, one can infer that the team did not capture:

A.

user stories

B.

milestones

C.

action items

D.

requirements

Full Access
Go to page: