Special Summer Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMI-200 Exam Dumps - PMI Agile Certified Practitioner (PMI-ACP)

Go to page:
Question # 17

During the project initiation stage, a team has estimated story points for all user stories. When the project team explained the minimum marketable feature (MMF), however, they were not confident that the solution would actually work.

What can the team do to better manage this situation?

A.

Deliver the minimum marketable feature (MMF) to customers for feedback.

B.

Write acceptance criteria for each business requirement to conduct proper testing.

C.

Develop test cases based on user stories.

D.

Ask the customer to provide acceptance criteria before developing the user stories.

Full Access
Question # 18

A project was delivered in a foreign country for a big customer, but there are a lot of complaints about the way the functionality was implemented. Now there is a new project to fix the defects of the first one.

What strategy should be used to deliver it successfully?

A.

Talk with the old project manager to learn about the problems they encountered and the lessons learned.

B.

Suggest organizing a meeting in order to analyze the situation and work to find a strategy.

C.

Analyze all defects and change requests carefully to understand their root causes and act accordingly.

D.

Suggest an iterative approach including timely engagement of all key stakeholders and hold regular review meetings.

Full Access
Question # 19

A team is transitioning from a predictive approach to an agile approach Historically, the team has delivered work products that did not meet customer expectations.

What agile practice can help the team to alleviate this?

A.

Test-driven development (TDD)

B.

Clear definition of done and regular demos

C.

Collaborative team planning games

D.

Consistent team velocity

Full Access
Question # 20

A large, corporate organization is forced to hire new team members in a geographically remote location from the current team. The manager of the department is concerned about the team not being colocated.

What behavior would indicate the team is not working well together?

A.

Team members are sending more emails to the team.

B.

The duration of feedback cycles has increased.

C.

The velocity has increased by having the new team work on items.

D.

New team members requested to move meetings due to time differences.

Full Access
Question # 21

In a project, the customer asks for a requirement that clearly deviates from the contract terms. How should the contractor react?

A.

Proceed with the work only after the contract is amended.

B.

Discuss the value of the change for the project with the customer.

C.

Evaluate effort and impact and ask for steering committee and shareholder approval.

D.

Stick with the contract terms and agree to review the requirement if time allows.

Full Access
Question # 22

In an adaptive environment, project managers use their skills and expertise to help the team adapt to changing circumstances and deliver to their stakeholders. While some agile practitioners may argue that the role of a project manager is not needed in self-organizing teams, pragmatic agile practitioners and organizations recognize that project managers can add benefit in many situations. The key difference is that their roles and responsibilities may look somewhat different in an adaptive environment.

What are some of the practices a project manager can bring to an adaptive environment?

A.

Building a collaborative decision-making environment with key stakeholders, teams, and sponsors.

B.

Ownership of detailed project planning, user histories, retrospectives, showcases and metrics board

C.

Ensuring agile values and principles are adopted by all teams involved in delivery of the project.

D.

Developing the project charter, writing the project plan, and following the achievement of all milestones.

Full Access
Question # 23

At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised.

How should this situation have been prevented?

A.

The team should have reviewed the definition of done prior to the iteration review.

B.

The testers should have ensured that test cases accurately reflected the product owner's expectations.

C.

The team should have conducted more demonstrations with the product owner during the iteration.

D.

The product owner should have provided clearer explanations during the planning meeting.

Full Access
Question # 24

A member of the development team displays disrespectful behavior and continuously argues with colleagues. This is negatively impacting team morale.

Which action should the scrum master take to resolve this situation?

A.

Mitigate the new conflicts that appear and rely on the self-organization of the team.

B.

Escalate the issue to senior management to make a decision.

C.

Follow the organization's policies to remove the team member to boost team engagement.

D.

Attend daily coordination meetings and retrospectives with the agile coach.

Full Access
Go to page: